The total investment of 107 projects is 124.58 billion!Yantai Huang Bohai New District La Manchu project construction "progress bar"

Author:Jiaodong Online Time:2022.07.27

Jiaodong Online July 27 (Reporter Jia Chuhang Correspondent Jiang Qian Wang Kai) Penglai International Airport's second phase of the main body was capped, Yantai High -speed Railway West Railway Station was undergoing foundation pit protection. Primary school is about to be completed and delivered ...

On the afternoon of July 27, the Yantai Huangbo Sea New District held a press conference to release the construction of key projects and key projects in the first half of 2022. It was learned at the meeting that in the first half of this year, the district had a total of 107 re -construction industrial projects and a total investment of 124.58 billion yuan, and 23 key project construction projects started, setting off a wave of key project construction construction.

Hundred industrial projects have opened work

At the construction site of Linglong Yingcheng International Hospital, the machine roar was endless, the workers were full of energy, and the project was undergoing the main construction. The hospital is the first major medical and health project of social capital investment in the district. It mainly builds three major sections of international hospitals, rehabilitation hospitals and high -end medical and nutrition centers. The first phase is planned to be capped at the end of this year. It has operating conditions in early 2024.

The project construction is a "locomotive" to promote economic development, and it is an important starting point for implementing "the economy must stabilize". This year, Yantai Huangbohai New District adheres to the concept of "grasping projects, grasping the big project", and made every effort to promote the construction of key projects. The total investment is about 43.3 billion yuan, 65 continued construction projects, a total investment of about 86.7 billion yuan, and more than 30 completed projects.

"Since the beginning of the year, we have started the project and restricted the bottlenecks. We have organized a series of tackling activities, coordinated and solved dozens of issues involving Huaxin Lihua and Wanshun New Materials Evaluation, China Resources Chemistry venues, and other dozens of problems. More than 20 infrastructure such as electricity, warmth, steam, and other infrastructure. "Leng Yi, director of the party group of the key project promotion center of Yantai Huangwohai New District, introduced Leng Yi, the director of the inspection and assessment office, especially this year, the weekly card real progress node node , Coordinate and solve the problem anytime, anywhere, ensure that 10 industrial projects including Yantai Optoelectronics Industrial Park and Akashi Technology, including Yantai Optoelectronics Industrial Park, and Akashi Technology, which have a total investment of 9.24 billion yuan.

In the first half of this year, the Yellow Bohai New District has opened a total of 107 re -work industry projects and a total investment of 124.58 billion yuan, of which 42 new industrial projects, a year -on -year increase of 20%.

Six primary and secondary schools are about to be completed and delivered

This year is the year when the construction of the Huangbo Sea New District is fully launched. The district highlights the focus of precision efforts, grasps the construction of key projects, and continues to enhance the image function of the city.

"In the first half of the year, we started 23 key projects, including 8 infrastructure projects, 14 public welfare projects, and 1 Yantai International Wine City." Said Fang Li, deputy director of the Construction Transportation Bureau of Yantai Huangwohai New District.

At present, the station building of Yantai High -speed Railway Station is undergoing foundation pit protection. The comprehensive transportation hub is undergoing earthwork construction. After completion, it will be jointly established with Yantai Penglai International Airport, Yantai Port West Port District, and Shugang Expressway. Multi -linking three -dimensional traffic system for iron and public. Tiandi Plaza South District's reconstruction and upgrading project is basically completed, and the paving is fully launched. It is planned to be completed by the end of October. The Tianshan Road Road Reconstruction Project has completed the construction of the western half of the pipeline and started the east half construction. After the reconstruction is completed, it will become a north -south landscape avenue. The Yantai International Wine City Project has completed the preliminary plan for the planning and design of the National Pavilion of the Wine, and is under optimization and adjustment.

The progress of school construction has attracted much attention. It was learned at the meeting that New Fourth Junior High School, Yuli Primary School, Yiyun Primary School, Xuefeng Primary School, Mucheng Primary School, and Fleeshan Primary School are about to be completed and delivered. %, 90%, 30%, experimental middle school South Campus, Mucheng Junior Middle School, Fulai Mountain Junior Middle School, Fengtai Shan School, and Hengshan Road Primary School are preparing before the construction and tender. The expansion project is preparing before bidding.

Continue to launch a hundred -day tackling operation

The concept of "project is king" is firmly established. Yantai Huang Bohai New District will continue to launch a hundred -day tackling. In the second half of the year, it will focus on promoting wheat shop technology, wearable temperature testing equipment, Wanhua special isocyanate integration, pilot pharmaceutical industrial park and other projects. Strive for more than 50 new industrial projects throughout the year and more than 30 completed.

"Especially the advancement of Penglai International Airport Phase II and Yantai West Station comprehensive transportation hubs, including the city's linked chart battle," said Leng Yi.

In addition, the district will plan a batch of projects next year, actively follow up the progress of land, energy consumption, procedures, etc., and promote the early construction and fast construction of the project.

- END -

Press conference | In the first half of the year, the city's economic market steadily operating the main indicators to speed up steadily

In the first half of the year, the city's economic market steadily operating the m...

Reading Chengdu | This first shop, landing in Chengdu!

Good morning! Welcome to ride--Published by Chengdu | News Morning BoatToday is Ju...