All units of the State Grid do their best to welcomes the summer power guarantee material guarantee

Author:State Portal Newspaper Time:2022.07.01

The soldiers and horses did not move, and the grain and grass first. Recently, the "two assurances" and "four elimination" work requirements of the National Power Grid Co., Ltd., and proposed that the material services were promoted to the "three strengthening and nine guarantees" of the "three strengthening, nine assurances" of material services. All units of the company strengthened their work organizations and responsibilities, took multiple measures, make every effort to make the procurement and supply of peak -summer engineering materials, make overall plans for emergency and epidemic prevention resources, strengthen emergency supplies guarantee, and ensure that high -quality completion of peak summer electricity insurance Support for material security tasks.

Guarantee the supply of peak -summer engineering supplies

The materials, infrastructure, and equipment of the company's units strengthened the coordination, re -sorted the peak -summer engineering supplies, carried out production inspections and resident urging work, prepared early, early production, early transportation, and early delivery to ensure supply.

On June 24th, the key project of Anhui Anqing Minsheng Guarantee, 220 kV Dafeng, was put into operation. More than three months ago, the transportation of the project -related equipment was affected by the epidemic. State Grid Anhui Electric Power actively negotiates with relevant government departments and equipment manufacturers to assist suppliers to complete the transportation tasks of main transformers and tower materials. The company also predicted the supply and demand situation early, optimized the procurement batch arrangement, strengthened the performance and control of performance, and focused on the timeliness of production and transportation.

Recently, ± 800 kV Baihetan -Jiangsu Special High -voltage DC projects ended with low DC system debugging and guarantee work. During the debugging and guarantee work, the State Grid Materials Company organized 88 suppliers of 247 on -site service personnel and 368 remote technology support personnel to complete 241 testing tests to achieve supplies, personnel in place, and service. At the same time, the company relies on the supply chain operating platform to monitor the provincial power company's supply and demand analysis of the supply and demand of key supplies in the supply and demand of key supplies. Plan, optimize the order of supply. At present, the 223 suppliers involved in this work are produced and supplied in an orderly manner to fully meet the needs of the main network of peak summer main network.

Prepare for emergency supplies

All units of the company strengthen emergency preparations, combined with experience and practices in natural disasters such as Henan's heavy rain in 2021, strengthen emergency materials protection drills and physical reserves, and build emergency capacity resource pools to ensure that "all -weather, full -time periods" can be provided in emergency conditions. Delivery service.

"The Weifang area has a large -scale power outage due to the affected affected. The details of the incident and the demand of the material have been reported. After receiving the call, the State Grid Shandong Electric Power Materials Department and Shandong Power Materials Company immediately launched an emergency response. State Grid Shandong Power Supply Chain The operation center is tightly and orderly carried out emergency guarantee work. Recently, State Grid Shandong Electric Power adopted provincial and municipal linkage methods to carry out special exercises for emergency materials protection. Through digital platforms, the full process lines such as emergency reporting, matching material needs, distribution plan generation, and transfer status of the goods were circulated. The level of emergency supplies guarantee capabilities and system functional practical level.

State Grid Henan Electric Power combined in 2021 Henan's heavy rain occurred in the case of short -term and surge in the needs of supporting networks and community supporting materials. ; Organize the exercise of flood prevention emergency supplies, complete the maintenance of flood prevention vehicles, emergency trains, and drainage squares and other flood prevention equipment to ensure the maintenance and use of the flood season.

State Grid Zhejiang Electric Power Materials Department collaborative professional departments, organize the update list of emergency materials reserve of the company's units, rely on the supply chain operation platform to monitor the data of the resource pool, arrange the inventory of the agreement, the physical resource reserves of the warehouse at all levels; Emergency materials partition, unblock e -commerce emergency procurement channels to ensure providing "all -weather and full -time" distribution services in emergency conditions; optimize and improve the function of supply chain operation platforms, support the rapid reporting of emergency materials, accurate matching supply, full process visual vision Can be checked.

Ensure the rapid supply of emergency supplies in disaster weather

All units of the company pay close attention to the early warning and response information of the disaster weather, and do a good job of cross -cities and provinces of provinces and provinces for actual resources, agreement inventory, order resources, and supplier inventory to ensure that emergency supplies are in place as soon as possible.

Since the flood in the flood, Hunan has repeatedly appeared in heavy rainfall. State Grid Hunan Electric Power heard the "flood". The company's material department launched the flood prevention emergency consultation and 24 -hour duty mechanism for the first time. The compound electric pole won the time for the rapid complexation of the Huaihua, the Miao Autonomous Prefecture of Huaihua, the Miao Autonomous Prefecture of the Xiangxi family.

Recently, severe flood disasters occurred in Longyan, Sanming, and Nanping in Fujian. Relying on the supply chain operation platform, the State Grid Fujian Power has carried out the work of territorial supplies, and the municipal materials deployment support of the city, coordinated the suppliers to transport them in advance, and established an efficient and transparent emergency material guarantee channel. During the guarantee period, the company's material department was equipped with a total of 135 kilometers of overhead insulation, 10.5 tons of steel core aluminum twisted lines, 1990 cement rods, 22 sets of sets of sets of equipment on the 400 kVA, 3 kilometers of low -voltage power cables, leakage electricity leakage 6,000 protectors, providing reliable supplies for fast re -power.

- END -

Modern technology helps Shaanxi pomegranate rise and grow

——In Shaanxi Pomegranate Industry Technology System Working Conference Two[Edito...

Stimulate the new vitality of the Chamber of Commerce in Jin to promote high -quality development with business promotion

Shanxi Evening News (Reporter Yue Wei Wang Shuang) From June 29th to July 1st, the company in the Jinshi Chamber of Commerce organized by the Shanxi Provincial Investment Promotion Bureau helped Shanx