Japan's one -nuclear waste re -processing plant cooling equipment occurs for about 8 hours

Author:Jilin Daily Time:2022.07.05

According to the Japanese Broadcasting Association (NHK) reported on the 3rd, on July 2, local time, the nuclear waste re -processing factory in the six villages in Sixtho, Aomori Prefecture, Japan suffered a failure, and its high radioactive nuclear waste liquid cooling equipment stopped running at about 3.30 pm on the same day.The shutdown lasted about 8 hours.

The operator, Japan's original Ran Company, said that the failure would not affect the external outside, but the Aomori County Government asked him to find out the reason and submit a countermeasure to prevent similar incidents from re -incidents.

Source: CCTV News Client

- END -