The rapid transformation of the West Second Ring Road in Hefei City

Author:Hefei Evening News Time:2022.07.20

West Second Ring Ring rapid transformation throughout the line to penetrate

On July 19, the second -ring transformation has made significant progress. The rapid transformation of the main line bridge of the West Second Ring (North Second Ring Road-Fanwa Road) is smoothly transformed, which also marks the entire line of the project in this section of the project and strive to have the release conditions for the release of the traffic in October this year.

West Second Ring: The main line bridge Heilong reproduces "Hefei speed"

On the morning of the same day, with the completion of the last connected concrete box beams, the main line of the West Second Ring Road (North Second Ring-Fanwa Road) was smoothly renovated, which also marked the entire line of the project's viaduct.

Since the start of the West Second Ring Road Fast Transformation Project on January 8, 2022, it lasted for 192 days. The node construction task was completed in advance to reproduce the "Hefei speed". This time, the dragons have laid the foundation for the establishment of the main line bridge in October this year.

The Western Second Ring Road Fast Transformation Project starts from Qingyuan Road in the north and Changjiang West Road in the south. The road is about 5.1 kilometers in length. The main line bridge is about 3.64 kilometers long. The main line of the traffic area is two -way six -lane, and the rest of the two -way eight lanes. The upper structure is a concrete box beam and steel box beam. There are 20 united concrete box beams and 24 -piece steel box beams, with a steel plate of 43,300 tons.

This project is the end of the second ring ring. It is of great significance for improving the construction of the second ring expressway network, serving the distribution transportation of Xinxi Station, and alleviating regional traffic pressure.

North Second Ring Road: When will the Tongling Road Interchange pass?

At present, along the North Second Ring Road, there are still some engineering projects under the Second Ring Road. Some citizens are concerned that the Second Ring Tongling Road Interchange is opened to traffic in mid -2022. It is now in July. When will the remaining ramps be released?

Relevant sources of the project unit said that the remaining ramps of the Interchange between the North Second Ring Road and the Tongling Road were opened, with a total of 4, all of which were iron -related ramps and were built by the railway department. At the end of the year, it was planned to be released at the end of June. Later, due to many factors, the overall progress will be pushed back.

The current plan is to strive to complete the bridge structure in July. After completing the auxiliary project in August, they try to have the release conditions as soon as possible to better provide convenient conditions for citizens to travel. He reports all media reporters Wu Qi/Wen Gao Bo/Photo Correspondent Ji Yungang Liu Yanyan

- END -

Heart the on -site service of the masses

It's so convenient, you can vaccinate the vaccine when you come to the community. ...

Active service to help the development of enterprises

In order to thoroughly implement the deployment requirements of the county's 10,00...