The latest progress of Huangshi tram and other projects!

Author:Huangshi Radio and Television Time:2022.07.30

On the morning of July 29th, the Second Paragraph Meeting of the Economic Situation Analysis Conference and Municipal Key Project Construction of the Municipal Key Project in the first half of 2022 was learned that the city's key construction projects in the first half of the year were steadily promoted. The specific progress is as follows:

Yellowstone Hyundai Tram Phase 1 project

The project planned to invest 1.866 billion yuan throughout the year, and the investment was 932 million yuan in the first half of the year, accounting for 50%. Among them, 90 % of the number of engineering volume was completed in the first bid segment; 85 % of the number of engineering volume was completed in the second bid segment; 95 % of the number of engineering volume was completed in the third bid segment; 70 % of the vehicle base completed the volume of the project, and 80 % of the total project volume was completed. At present, it is promoting the construction of rail paving, power supply, communication signals and vehicle bases. It is expected that "Eleventh" will be opened to traffic.

Comprehensive rectification project of the Yangtze River Section of Huangshi City

The project planned to invest 1.597 billion yuan throughout the year, and the investment was 741 million yuan in the first half of the year, accounting for 50%, and 70%of the total project volume was completed. At present, the surplus project volume of the mining machine to the Zhongyao bridge section is planned to be completed by the end of September 2022.

Guilin South Road Reconstruction Project

The project planned to invest 200 million yuan in the first half of the year to complete the investment of 24 million yuan, accounting for 12%. At present, the project construction unit has entered the construction of the secondary aviation bureaus to carry out the bridge of the co -line section of the tram, and the upper structure bracket construction. It is planned to complete the upper structure construction of the co -line bridge at the end of October 2022.

Urban Broken Road Reconstruction Project

15 pieces of broken roads in urban areas have started 12 and 3 preliminary work, with an operating rate of 80%. The 2022 planned investment was 439 million yuan, and the investment has been completed 205 million yuan, and the investment accounts for 46.7%. Among them, the Guangzhou Road West Extension Project completed 66%of the total project volume. At present, the construction of water stabilization and asphalt paving is currently planning to open to traffic by the end of December 2022. The Suzhou Road West Extension Project has completed 60%of the total project volume. At present, the retaining walls and asphalt paving construction is currently being opened to traffic at the end of December 2022.

Xincheng Avenue (Olympic Avenue) West Extension

The project 2022 plans to invest at 80 million yuan, and now has completed investment of 200 million yuan, 26%of the investment is completed, and 80%of the total project volume is completed. At present, the construction of the asphalt paving of the Beizuan Road is being implemented, the construction of the roadbed drainage pipeline of the south -south road, and the project plans to open to traffic in mid -August 2022, and open to traffic at the end of September.

History and cultural district protection and repair and cultural tourism utilization project of the old site of Huaxin Cement Plant

The project 2022 plans to invest 625 million yuan. In the first half of the year, the investment was 60 million yuan, and the investment proportion was 9.6%. Among them, 90%of the project volume of the 1-3 kiln of Wenbao District has been completed, and 80%of the completion of the completion of the project in the east of the repository; the two Wenbao projects of the slag library and the new stall station are promoting the acceptance of cultural protection and acceptance; the Central Cultural Zone The B plot has all been capped to carry out internal and external wall decoration construction; 50%of the total project volume was completed. At present, the asphalt paving construction is planning to open to traffic in December 2022.

- END -

Xinhua Full Media + 丨 China National Edition Museum is completed in Xinhua All Media + 丨 China National Edition Museum to complete

On July 23, the Chinese version of the National Edition of Beijing was settled at ...

"Epidemic Prevention and Control · Authoritative Release" Silver City orderly promotes the prevention and control of the epidemic situation

Press conference on the press conference of Baiyin City New Guanye Pneumonia.New G...