Some are idle and some extension, three public parking lots in Jinan have not been put into use according to the plan

Author:Qilu Yiyi Time:2022.08.07

Reporter Yu Yue Xia Hou Fengchao

On August 7, the "Face the Problem Practice Promise" large -scale TV questioning program- "Main Style Supervision Facial Face" was opened. At the time of questioning the government, in response to the fact that the three public parking lots in Jinan were not put in accordance with the plan, the residential construction department and the district leaders responded on the spot.

In the short film, in 2018, the Jinan Municipal Planning Bureau compiled the "Three-Year Construction Plan for the Public Parking Lot in Jinan City", which is planned to build 81 public parking lots in 2018-2020. The Jinan Housing and Urban Construction Bureau is responsible for organizing, guiding, and urging the construction of the entire parking lot in accordance with the plan. According to the end of the Jinan public parking facility construction project in July 2021, it was released from the account of the public parking facility construction project, and the new underground garage of the Chengfeng Flour Plant of the Bridge District was completed on December 1, 2020. However, on July 15, 2022, it can be seen in the parking lot that the two entrances and exits of the north and south have been blocked, and 107 parking berths are idle.

Another planned construction of the Northern Parking lot of the planned construction has repeatedly delayed the construction period. On September 14, 2021, the Jinan Housing and Urban Construction Bureau promised that the parking lot can be completed and used by the end of 2021. However, on July 5, 2022, the person in charge of the project construction said that if the progress is smooth, the parking lot can only be put into use in November.

In addition, the ledger also shows that the completion time of the internal parking lot of Yinfeng Garden should be in January 2019, but it has not started construction so far. On September 14, 2021, the Jinan Municipal Housing and Urban Construction Bureau promised to negotiate with Yinfeng Group to rebuild it into a three -dimensional parking lot and open to the public. However, the survey found that the region has not built a three -dimensional parking space in recent years. In addition, security personnel in the area said that the community is a closed community and does not allow foreign vehicles to enter.

At the government, the new underground garage was built on the Tianfeng Flour Factory of Tianqiao District. The relevant person in charge of the Tianqiao District said that the garage and ground projects were supporting. At present, the ground project has not yet been officially transferred, and it will be actively connected and actively enabled.

In response to the north parking lot of the Huangting Stadium, the relevant person in charge of the Party Urban Construction Department of the Jinan Housing Urban and Rural Construction Bureau said that the parking lot was led by the Lixia District Government and officially started in January 2021. It was affected by the reasons such as the college entrance examination and the scum clearance, which caused the construction period. At present, the main body of the parking lot has been completed, but there are still problems with intelligent parking equipment and funds. At the government, the relevant leaders of the municipal housing and construction department and the Lixia District Government would go all out to ensure that the parking lot can be put into use before October 1 this year.

Regarding the problem of the parking lot on the north side of the Emperor Ting Stadium, the person in charge of the Urban Construction Office of the Jinan City Housing and Urban Construction Bureau introduced that the parking lot on the north side of the Emperor Pavilion Stadium was led by the Lixia District Government. This parking lot was in June 2020. If the joint meeting determines the construction, land acquisition and demolition began in July. Construction started in January 2021. Because the parking lot is in the bustling area of ​​Quancheng Road, the operating surface is relatively small. It is a total of 166 parking spaces on the two floors of the ground underground and above ground. It is difficult to clear the residue and affect the construction period. The main body of the parking lot has been completed. This year, because of the smart parking equipment, it has not entered the market to affect the construction, and has recently been connected with them to prepare to enter the field. Strive for operation on October 1.

In response to the Yinfeng Garden parking lot, the party secretary and director of the Jinan Housing and Urban -Rural Development Bureau said that the site selection of Yinfeng Garden parking lot was originally on the north side of Yinfeng Garden and within the protective green space of the river. Essence Later, after studying the joint meeting of the city central district, a building in Yinfeng Garden was transformed into a parking lot. After the transformation, it has been enabled. Obstacles.

According to the relevant person in charge of the city in the city, the situation in the region will be combed in the near future, and the next step will be eliminated.

- END -

People's Daily Vlog | 2022 Changchun Summer Art Festival opening

Play the main theme of the summer: high temperature, fighting heat, keeping safety and stable production

This week, the hottest sector in the country is the Yangtze River Delta. Under the...