How to brighten the "face value" of the city?Just create "Luohe Speed" in only 20 days

Author:Dahe News Luohe News Time:2022.08.16

Dahe Daily · Yu Video Reporter Liu Guangchao Correspondent Chen Guo Luan Wenqi

At 7 o'clock on August 15th, with the last enclosure and demolition, Liaoshe Road's sidewalk unblocked project was completed in advance, and the two sides of the Xiliaohe Road of Songshan Road changed from two -way four lanes to six lanes. Effectively alleviated the traffic pressure at the intersection of Liaohe Road, effectively solved the pain points of the difficulty of traffic in the traffic, and comprehensively ensured the safety of the people's travel, and provided hardware support for the construction of a higher level of national civilized cities in Luohe.

The Liaoshe Road Portal Road Unobstructed Project was started on July 26, 2022. It is planned to be fully completed on August 16, 2022. Luohe Housing and Urban -Rural Development Bureau shall specifically undertake the construction task of the project, coordinate and scheduling, carefully plan, strict management, inverted, inverted, and inverted. With the strong support of the Tancheng District Party Committee and the District Government, the city management, traffic police, pipelines and other departments, and the joint efforts of participating parties, have completed all projects in just 20 days to complete all projects. The construction task not only submits a satisfactory answer to the municipal party committee, municipal government and the general public, but also creates "Luohe speed" from all aspects such as engineering design, construction, construction, supervision and guarantee. "Luohe Speed" benefits from the "face value" of the first -tier workers' fighting high temperatures and sweating like rain like rain. Thanks to the "nanny" of the project, the promotion of the construction of the building, the service, and the dedication to the project.

Promoting high levels, coordinated scheduling. Facing the characteristics of the project's "tight time, heavy task, and high standards", the Municipal Housing and Construction Bureau attaches great importance to it. The cost consulting team and the comprehensive coordination group, in advance and judging the problems in the promotion of the project, and the "nanny" comprehensive service project construction; invite relevant departments to work in charge of the comrades on the spot, clarify the specific contacts of various departments, assign special personnel and responsible units to all responsible units Docking, multi -unit linkage to ensure the smooth implementation of the project.

Plan carefully and design carefully. The technical service team of the municipal engineering construction headquarters, together with the relevant experts of the design unit, is based on the importance and particularity of the project, from the perspective of vehicles and pedestrians, construction organizations, landscape design and other angles, and in depth the front line of the scene gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually gradually graduallyteteu Touch the various issues before the renovation of the row intersection, solicit opinions of various departments and the masses, summarize more than 20 suggestions, repeatedly demonstrate and optimize the plan. In less than 2 days, a design plan that can be operable and investment is formed.

Strict management and fine construction. In order to ensure the minimum impact on the normal travel of residents, starting from the minimum, standardized management is required, and the construction unit is required to hold a safety class meeting daily to meet the safety risks and construction quality points of construction operations; On the basis of ensuring the safety, firmness, and reliability of the enclosure, consider the impact of the safety of the travel of the surrounding merchants and residents, and set up a public welfare advertisement on the fence to make the enclosure become a promotional position for civilized construction. Make noise operations; do a good job of dust prevention and control, strictly implement the "six 100%" to ensure that the field is clear.

The inverted construction period, the stubble is advanced. Assign special personnel to serve as the person in charge of the construction unit project, 24 hours of integrated scheduling construction, supervision, design and other participating units on the spot, strictly follow the established scheme construction, find the problem on the spot to ensure that the problem is solved "no more than noon, no night"; requesting The construction unit is discharged from the construction progress of the construction progress to make a reasonable plan to clarify the time limit of each process; in the face of extreme continuous high temperature weather, guide the formulation of high -temperature construction emergency plans, and adopt a variety of heatstroke cooling measures to effectively ensure construction safety and engineering progress.

- END -

"Deyang" Luojiang District promotes and implemented the spirit of the city's grass -roots united front work in the second quarter

After the on -site promotion meeting of the grass -roots united front work in Deya...

@Everyone, let's take a look at the "Good Internet users" event of the Anhui Trade Union!

The 20th National Gong Gong Gong Gifts of the Positive Employees of the Net2022 An...