More than 200 tons of steel are here!

Author:Tianshan.com Time:2022.08.25

Pomegranate/Xinjiang Daily (Reporter Sun Fangting reported) "Steel is coming!" At around 16:00 on August 25, the door of the construction site of Urumqi International Textile Center project slowly opened. After the disinfecting, I entered the construction site.

Watching the cranes put more than 200 tons of steel into the warehouse one after another, Zhang Liangjian, deputy general manager and safety director of Urumqi International Textile Center Investment Development Co., Ltd., became even more at ease.

On August 25, at the construction site of the Urumqi International Textile Center project, the crane was unloading the transported steel. Photo by Tian Juan

As of August 25, 1929 tons of steel and 5800 cubic meters of concrete that continued to enter the construction site ensured the normal construction of the project.

After implementing temporary static management measures in key urban areas of Urumqi, the construction site was opened at the construction site of the project. A large number of IV steel, concrete and transportation problems required for the project construction made Zhang Liangjian anxious. It will not be delivered on time.

In desperation, Zhang Liangjian contacted the Urumqi Economic and Technological Development Zone (Tutun River District) Construction Bureau (Transportation Bureau, Water Affairs Bureau, People's Defense Office) director and deputy secretary of the party group.

"Don't worry, we will coordinate the pass for you now. We will immediately help you find the building materials suppliers we need." Song Xinzheng said "reassurance pill" for Zhang Liangjian.

Song Xinzhang coordinated with the Urumqi Economic Development Zone (Tutun River District) Industry and Information Bureau, Urumqi Economic Development Zone (Tutun River District) Development and Reform Commission, and other relevant units coordinated to determine the building materials suppliers that could be guaranteed. Essence

"After getting these things, I'm relieved." Zhang Liangjian, who was worried about the night, finally relieved at this moment.

In order to ensure the smooth progress of the project, the relevant departments of the Urumqi Economic Development Zone (Tutun River District) and Zhang Liangjian understand the construction site with Zhang Liangjian every day. Materials and epidemic prevention materials.

Song Xinzhang said that after the key urban area of ​​Urumqi implemented a temporary static management measures, the Urumqi Economic Development Zone (Tutun River District) Construction Bureau quickly established 10 epidemic prevention and control teams, arranged the demand for building materials in the construction site in the jurisdiction, and coordinated the issuance of vehicle traffic permits in a timely manner 235, as of now, a total of about 72,000 cubic meters of concrete in the jurisdiction and about 11,000 tons of steel.

- END -

@所有!Pay attention to the "package baby" trap in purchasing

PurchaseA way of transaction that people often choose nowadaysThis can often buy d...

Comprehensive deployment of in -depth and in -depth pollution prevention and control battles

On the afternoon of July 26, the Yanji City Branch of Yanbian State Ecological and Environment Bureau held a meeting of the key task deployment deployment of the 2022 of Yanji City's in -depth polluti...