The first phase of the new industry can be aggregated formaldehyde project enters the countdown countdown

Author:Tianshan.com Time:2022.08.26

Tianshan News (Reporter Shi Xin reported) "Under the premise of strictly implementing the epidemic prevention and control measures, we used it as two days a day to keep an eye on the time limit of the first phase of the formaldehyde project, the progress of the construction site, and the quality control of the project. Ensure that the project will achieve a linkage test at the end of September. "On August 26, Wu Wenzhao, the person in charge of the first phase of the formaldehyde in Xinjiang New Industry Energy and Chemical Co., Ltd., said that the overall progress of the project has completed 85%and entered the countdown sprint stage.

The first phase of the formaldehyde project triple formaldehyde and dioxide rings device area. Photo by Zhang Kang

The New Industry Energy Polymerization Fdedehyde project is a key project of the Xinjiang Production and Construction Corps and the State -owned Assets Supervision and Administration Commission of the Autonomous Region. It has a total investment of 2.8 billion yuan. The first phase of the project (40,000 tons/year) was launched in April 2021. Relying on the new industrialized methanol resources, the project adopts advanced and mature and stable aggregate technology and equipment from abroad to produce new coal -based materials -polymerized high -molecular resin, which will fill the gap of Xinjiang polydehyde products after production.

On August 26th, at the construction site of the new industrialization polymerization formaldehyde project, the rumbling machine roared the construction site, and the workers were sweating like rain. Various mechanical equipment was full of horsepower, and the countdown card was eye -catching.

"At present, 668 main device process equipment has arrived at 633 units, and 532 units are installed. Circular water stations, fire water stations, and public engineering stations have been completed." Li Kun, deputy manager of the formaldehyde project, said.

The project resumed work on March 10. However, due to the epidemic situation in Shanghai, Jiangsu and other places, the main device production and transportation of the formaldehyde projects were blocked, and the project time was delayed.

time does not wait! In the face of emergencies, the leading group of the Construction of the Fulfide Project Coordinating Command Engineering and Technology Department, Production Management Department, and Technology Quality Department of Technology to establish a "one game of chess" ideas. Pay close attention to the quality control of the project, keep an eye on the prevention and control of the epidemic, and ensure that the project construction is effective and seeking breakthroughs.

It is reported that in order to ensure the quality and accelerate the progress, the project construction leadership group adheres to the promotion coordination meeting every day, finds shortcomings, analyzes the causes of the problem, solves the difficulty of contradictions, and lays the foundation for the project linkage test and normal production and operation.

- END -

Temporary seal!Two business places in Yinzhou Yi County use combustible materials decoration

A few days ago, the Jinzhou Yixian Fire Rescue Brigade continued to conduct fire s...

[Learn and implement the spirit of the 14th Provincial Party Congress] Interpretation of the 14th Pa

The "semi -finals" action is the strategy to realize the "five promotion" (1)E...