Five highways in Shandong Province were completed and opened to traffic during the year

Author:Jinan Daily Time:2022.08.29

On August 28, the reporter learned from the Shandong Provincial Department of Transportation that there will be 5 high -speed opening of Shandong Province in the year of Shandong Province. The earliest expected is expected to be at the end of September, and others in November and December.

In 2022, Shandong Province planned to build 6 projects including Jinan to Gaoqing and Zhanhua to Linzi, with a total of 468 kilometers. At present, the project of the projects from Malan Tun to the Lusu world from Xintai to Taierzhuang Highway has been completed, and the remaining five projects have made a smooth progress, laying a solid foundation for achieving the goal of breaking 7,800 kilometers at the end of the year.

The total length of the Jinan to Gaoqing Highway is 93.3 kilometers. The 27.4 kilometers of the Dadong Ring to the Yellow River Hub of Jinan uses two -way 6 -lane standards. The 65.9 kilometers of the Yellow River Hub to the Changshen Highway uses two -way 4 -lane standards. Construction started in March 2020. The construction of the main project is basically over, and the payment and acceptance work is being carried out. It is expected to be opened to traffic by the end of September.

The total length of Jining New Airport to Zaohe high -speed section is 59.7 kilometers. The two -way 4 -lane standards are adopted throughout the line. Construction started in March 2020. The control engineering has been lifted across the Baima River Bridge, and the adjacent section of the turntable bridge has been completed to achieve the entire line of penetration. At present, the road -based projects and housing construction projects have been completed 100%, the bridge Han project is 98%, the pavement project is 86%, and the security project is 60%. It is expected to be opened to traffic in November.

The total length of Zhanhua to Linzi Highway is 107.7 kilometers, and the two -way 6 -lane standards are used. Construction started in November 2019. The main tower of the Yellow River Bridge in the control engineering has all been capped, and the main bridge has closed. At present, road base engineering, bridge culvert projects, and housing construction projects have been completed by more than 95%, pavement projects have been completed by 86%, and 59%of the intersection projects have been completed. It is expected to be opened to traffic in November.

The total length of the Weifang to Qingdao Highway and the connection line is 130.2 kilometers, and the two -way 6 -lane standards are used. Construction started in June 2020. The first section of the control engineering cross -iron rotor bridge has been completed, and the transfer is expected to be carried out in October. At present, the road -based projects have been completed 98%, the bridge Han project is 95%, the pavement projects are completed 74%, the housing construction project is completed by 50%, and the intersection project is completed by 37%. It is expected to be opened to traffic in December.

The Heze section of Puyang to Yangxin Expressway is 66.9 kilometers in length and uses two -way 4 -lane standards. Construction started in June 2020. Controlling engineering Caozhou Hub's interoperability was connected in July. At present, the project road base and bridge projects have been basically completed, the main line line has been connected throughout the line, the pavement projects have been completed by 70%, the housing construction projects have completed 62%, and the mechanical and electrical and traffic safety projects are completed by 20%. It is expected to be opened to traffic in December. (Jinan Daily reporter Dai Shengbao)