Build a sponge city, Yueyang issued this "Measures"

Author:Yueyang Evening News Time:2022.06.20

How to build the construction of sponge cities in Yueyang City? How to control it? The reporter learned from the Municipal Housing and Urban Construction Bureau that the Municipal Government Office issued the "Administrative Measures for the Construction of Sponge City, Yueyang City" (hereinafter referred to as the "Measures"), which will be implemented on June 13, 2022 for 5 years.

What is a sponge city?

Sponge cities refer to the management of urban planning and construction and giving full play to the effects of absorbing, exudating, and slow release of ecosystems such as architecture, roads and green spaces, and water systems to effectively control rainwater runoffs and achieve natural accumulation, natural penetration, and natural purification Urban development method.

The construction of sponge cities should follow the basic principles of ecology -oriented, natural circulation, planning guidance, system promotion, government guidance, social participation, comprehensive integration, and overall implementation.

Where is the "Measures" suitable for?

"Measures" suitable for various types of sponge cities in Yueyang City City (including Yueyang Building District, Yunxi District, Junshan District, Yueyang Economic Development District, Chenglingji New Port District, Nanhu New District) Activity.

Integrated into the city's overall planning

When compiling or repairing the overall planning of the city, the detailed planning of the city, and the relevant special planning of roads, green spaces, water, etc., the sponge cities should be compiled (special), and the total runoff control rate of the annual runoff of the rainwater should be used as a rigid control indicator to determine the construction land. Indicators such as the total runoff control rate.

When preparing or renovating the overall planning of the land space, the natural resources and planning departments should fully implement the concept of sponge city, compile or repair special planning for urban vertical, road, green space, water system, water resources, drainage and waterlogging, ground space and other special plans It should be fully connected with the special planning of the sponge city to implement the requirements of sponge cities.

According to the special planning of the city -level sponge cities (management committees) in the city urban area, in accordance with the actual situation of the region, they organize the preparation of district -level sponge city construction planning.

How to build management?

All kinds of new, renovated, expanded construction projects, urban renewal, old community reconstruction, environmental improvement and other reconstruction construction projects must implement the concept of sponge city construction.

At the stage of the project preliminary design plan and construction plan design plan, the construction unit should provide a special (special article) design (special article) design of sponge city construction, implement the requirements of sponge city construction planning indicators, and reasonably select the scale of sponge facilities. The project plan shall meet the planning conditions of sponge cities, and can effectively guide construction and construction. Construction units shall organize experts to review the design of the plan and meet the requirements of sponge cities such as land transfer planning conditions, and submit the design schemes that have been approved to be approved by the residential construction department.

In the case of special circumstances, if you need to adjust the conditions for the construction of the sponge city construction, you should apply to the housing construction department and submit the annual runoff control rate control rate adjustment plan.

The "Measures" also stipulates that during the implementation of the project construction, the construction unit is responsible for implementing the planning indicators of sponge cities, and in accordance with relevant national, provincial, and municipal regulations, standards, and requirements, the construction concept of sponge cities penetrates the project planning, design, construction, construction, construction, construction, construction, construction, construction, construction, construction, and construction In the process of acceptance, operation and maintenance, do a good job of project construction management.

The construction unit shall be carried out strictly in accordance with the requirements of the design drawings that are qualified, forming a complete sponge facility construction technical information, and promptly prepare for inspection.

The supervisory unit shall perform the responsibilities of engineering supervision in accordance with national laws and regulations, effectively ensure that the raw materials enter the site for inspection and then use, and ensure that the project construction is implemented strictly in accordance with the design drawings.

The completion and acceptance of sponge city facilities shall be implemented in accordance with the relevant construction acceptance specifications and standards, and the project construction unit shall organize the design, construction, engineering supervision and other units, and the housing construction department can be delivered after the supervision and acceptance of the residential construction department can be delivered. Before the completion acceptance, the construction unit shall submit the evaluation report of the sponge city construction effect to the housing construction department and be included in the construction project completion documents.

The housing construction department shall strengthen the full supervision of various new, reconstruction and expansion projects.

How to run and maintain?

Sponge facilities should follow the principle of "who invest in and who manages" to determine the operation and maintenance unit in a timely manner. The sponge facilities of government investment construction projects shall be supervised by relevant departments in accordance with the division of responsibilities, and entrust the management unit for operation and maintenance. The sponge facilities of the social investment construction project shall be responsible for operation and maintenance shall be responsible for the owner of the facility.

The operation and maintenance management unit of sponge facilities shall establish a maintenance management system and operating procedures in accordance with relevant requirements such as operation and maintenance, strengthen daily inspections, maintenance and maintenance, and ensure that the facility function is normal and efficient. Encourage the operation and maintenance unit to evaluate the operation and maintenance effect of the project through online monitoring and other methods, and continuously improve the efficiency of operation and maintenance.

The housing construction department shall establish a comprehensive sponge city construction platform to provide support for the construction and operation, assessment and evaluation of sponge city facilities through digital information technology.

How to supervise?

The "Measures" pointed out that if the relevant units such as construction, planning, design, construction, supervision, operation and maintenance violate the provisions of these Measures, the relevant authorities can see the serious circumstances, investigate the relevant responsibilities in accordance with the law, The unit is included in the list of dishonesty.

Source: Yueyang Daily

- END -

Follow | The first case in the province!Patients with severe cardiopulmonary function supported by ECMO complete long -distance transportation

Patients with severe cardiopulmonary failure supported by medical care using ECMO ...

Pan Yue is the secretary of the party group of the National Ethnic Affairs Committee

According to the official website of the National Ethnic Affairs Commission, on the afternoon of June 18, 2022, the relevant responsible comrades of the Central Organization Department attended the me