The first domestic waste incineration power plant in our city is about to operate

Author:Shaoyang Daily Time:2022.06.23

Yun Shaoyang client June 23 (all media reporter Liu Bo correspondent Wang Linlu Tang Wenfeng) How to dispose of urban domestic garbage, many cities had a headache for it. In Shaoyang, urban domestic garbage is about to become a treasure, becoming a continuous sources of raw materials for power plants. On June 22, the reporter learned from the project department of Xin Shao's domestic garbage incineration power plant that the project will ignite at the end of June and become the first domestic garbage power plant in our city.

Project overlooking map

The project is located in Xintianpu Town, Xinto County, and was undertaken by Everbright Environmental Energy (Shaoyang) Co., Ltd.. The project (Phase I) covers a total area of ​​84 acres and a total investment of 654 million yuan. After the project is put into production, it is expected that the daily treatment can reach 1,000 tons and the annual power generation is about 130 million kilowatt -hours. The comprehensive utilization of renewable resources, ecological tourism, green vegetation and environmental protection education in the central part.

Tape of the project

Huang Nengbin, deputy general manager of Everbright Environmental Energy (Shaoyang) Co., Ltd., said that after the project is running, domestic garbage from various places will be burned through boilers to generate steam for power generation. At the same time, the flue gas generated by incineration, after the SNCR+semi-dry method+activated carbon jet+dry powder injection+cloth bag dust removal, can meet the "domestic waste incineration pollution control standard" (GB18485-2014) and the European Union 2010 (2010 /75/eu) standards to achieve standard discharge.

The project started construction in July 2021. New Shao County listed it as the county's key livelihood project project. The county established the command of the waste incineration power generation project for the first time, implemented the leadership responsibility system, raised the promotion mechanism, integrated the advantages of land and other resources, and promptly help solve the problem of difficulties and blocks, forming a strong joint force to promote project construction. The county -level cadres, the heads of relevant functional departments, the "two committees" of the village, and residents around the project went to the waste incineration power generation projects of Yiyang, Changsha and other places in Changzhou, Jiangsu, to learn from the scriptures, learn advanced experience, and eliminate the concerns of the people around the project. In order to ensure the progress of construction, Everbright Environmental Energy (Shaoyang) Co., Ltd. mobilized its strength from all over the country, supplemented by people, and arranged more than 500 people to saturate at the scene every day to work through "five plus two" and "white and black".

The project construction runs out. "In less than a year, the project chimneys and factory buildings have been built, and the equipment such as boilers has also been installed. The comprehensive building enters the final internal decoration stage, and the entire project has begun to enter the countdown." Huang Nengbin introduced that the overall progress of the project construction construction is currently the progress of the project construction construction. About 80 % is completed, and the ignition will be tried and run at the end of this month. It is expected to be officially put into production at the end of September.

The reporter learned from the Office of the Municipal EIA that Shaodong City, Dongkou County and Wugang City are also making every effort to promote the construction of domestic waste incineration power generation projects. At present, the overall project of the Shandong City project has been completed by more than 50%, and it is expected to ignite the trial operation on September 30; the preliminary project of the Dongkou County project is basically completed to strive to ignite the trial operation within the year; the Wugang project is stepping up the preliminary work.

- END -

Meteorological Observatory of Korqin District, Tongliao City, Inner Mongolia issued a thunderbolt ye

At 11:17 on June 09, 2022, at 11:17 on June 09, 2022, the 6 -hour Nickelqin area may occur. Local regions are accompanied by strong streaming weather such as short -term and strong precipitation, thun

Last night, the super moon is now in the night sky!This year's "second largest full moon" launched!

On June 14, Super Moon appeared in the night sky, which is also the second largest...