Xiuyu: Inconsistent with the substation to ensure the cool summer of the coastal residents

Author:Putian released Time:2022.06.25

"The fifth full voltage impact of the main change of the 110 kV Mountain Star 2 is successful, and the equipment is normal." At 13:32 on June 23, with the sound of the buzzing of the main transformer, the Putian Power Supply Company of the State Grid completed the 110,000 yuan. The Fushan Star Transformer Power Station added No. 2 main transformers to send power, ending the current status of the single main transformer operation of the substation, greatly enhanced the reliability of power supply reliability of Pinghai Town and the surrounding township power grids.

The 110 kV Shanxing substation is located in Shanxing Village, Pinghai Town, Xiuyu District. In February 2019, the main transformer No. 1 of 110 KV Shanxing Transformer Power Station was put into production. However, due to the rapid economic development of coastal areas in the past two years, the original 50,000 volt transformer capacity has not met the needs of a substantial increase in local economic load. In December last year, Putian Power Supply Company launched the Shanxing Transformer Power Station to add No. 2 main transformer expansion project, adding a 50,000 volt transformer and 10 volt lines for 12 times to comprehensively improve the power supply capacity and power supply reliability of the coastal regional power grid.

During the construction of the project, the relevant departments of the company's departments cooperated to combat, promote efficiently, strictly control the safety of production, coordinate and solve problems in the construction process, overcome the difficulty of time and high construction risk factor, and under the premise of ensuring safety and quality , Orderly promote engineering construction. In order to ensure the successful investment of the project, the company formulated detailed suspension, electricity delivery plans and emergency emergency plans in advance, and carried out special patrols for equipment to ensure that the equipment was launched with zero defects. On the day of the delivery, the staff fully analyzed the danger point in the operation process, made emergency plans to ensure that the startup process was foolproof.

"In order to ensure the electricity consumption of the surrounding residents, we have been completed and put into operation before the weather is hot." Said Xue Yongcheng, a transformer project manager of the Putian Power Supply Company Construction Department, said that the main transformation project is the focus of Putian Power Supply Company to welcome the peak summer project. After the production, not only further strengthened the structure of the coastal regional power grid, optimized the operating method of the grid, met the needs of the future load development of the head and Pinghai area, but also added a strong guarantee to the electricity of the coastal residents this summer.

(Source: Fujian Daily · New Fujian Client Reporter: Chen Han'er Correspondent: Chen Na Li, Editor: Wu Wei)

- END -

From 18:00 on the 23rd to 11:00 on the 24th, Wuhan's largest cumulative rainfall reached 108.9 mm

On the evening of June 23, 2022 (18 o'clock), it began in the northern part of the...

Lucheng, Wenzhou, Zhejiang: Practicing green carbon reduction co -construction of beautiful homes

Green travel, garbage classification, CD -ROM operation, energy saving and consump...