[Improve efficiency, improve efficiency, increase efficiency] The first month of the new driving training ground in the province will be basically completed next month

Author:Today Time:2022.07.09

On July 5th, the construction site of the construction site of the driver of the motor vehicle driver of Putian City was busy: 7#8#building brick paving, 9#building ceiling and outdoor supporting construction are advancing in an orderly manner.

The relocation project of the municipal motor vehicle driver training site is located in Xixu Village, Huating Town, Chengxiang District. It is the general contracting project of the EPC project. The total investment of the project is about 350 million yuan. Plan and build large -scale automobile examination venues, small car examination venues, motorcycle examination venues, special examination sections, etc.

According to reports, the project was officially started on June 18 last year and was divided into two plots for design and construction. The land plan is planned to be a small car test venue and a motorcycle examination venue. Among them, there are 6 test channels for the second examination venue of small motor vehicles, including 3 manual transmission examination channels and 3 automatic transmission examinations; Two wheel motorcycles and one three -wheeled motorcycle examination. At the same time, build a small training site for small car subjects, set up 2 small automatic transmission motor vehicle training channels and 1 small manual transmission training channel. Land 2 is a large car test site. Due to terrain restrictions, the second test of large -scale car subjects is designed in the form of a library. Large trucks and large passenger cars are used with 1 test lane, China -Pass and traction cars are used with 1 test lane.

It is reported that the project is the first test site in the province to adopt a partition design model. After completion, it will become the first model of the province and the second large truck test field in the province.

At present, all buildings have been capped in structure, wall masonry and painting inside and outside the buildings are basically completed, and indoor decoration has also completed 40%of the project volume. The slope support has completed 90%of the project volume, the outdoor facilities have completed 30%of the project volume, and the construction is expected to be basically completed in August.

Source: Rong Media Center, Chengxiang District, Putian City

Edit: Lin Youming

- END -

Haidian District played the role of bond funds to expand effective investment to promote high -quality development

The reporter learned from the District Finance Bureau that as of now, all the new bond funds in our district have been issued in 2022, and a total of 17.782 billion yuan in bonds have been won, of whi

Yulin Zizhou County Aging Health Service Center launched the "Silver Age" to take the gras

On June 13th, in order to further promote the promotion of the health of the elder...