Provide sufficient power protection!Songjiang's first large -scale transmission and transformat

Author:Shanghai Songjiang Time:2022.06.14

With the successful completion of the No. 1 main transformer impact test, recently, 110 kV Tangming substation built by State Grid Shanghai Songjiang Power Supply Company entered a 24 -hour trial state. This is the first large -scale transmission and transformation project in Songjiang Grid this year, which will provide sufficient power guarantee for the re -production of enterprises.

The 110 kV Tangming transformation station is located in Shidang Town, Songjiang District. It is a key construction project for electricity to welcome the peak summer this year. The construction scale is 2 main transformers with a capacity of 50 mega security. The 110 kV lines are built 4 times and the 10 kV lines are 32 times. The investment in the substation will further optimize the structure of Songjiang Power Grid, adding a variable capacity of 100,000 kilowatts, effectively alleviating the electric pressure in the Shihuang area, and meeting the power demand for the subsequent upgrading and transformation of the town industrial park.

Since this spring, affected by the epidemic, the construction of the substation has stalled at more than February, which has brought challenges to the completion of the project as scheduled. To this end, Songjiang Power Supply Company decided in advance and took the lead in resume the project on May 7. The construction of resume work strictly follows the requirements of "one hand to grasp the epidemic prevention and control, grasp the re -production and re -production in one hand", and flexibly adjust the progress of the project according to the changes in the situation of the epidemic situation to compress the construction period. At the same time, managers also use the "re -work code" to strengthen personnel entry control, formulate a number of epidemic prevention measures such as in batches, temperature and disinfection, daily nucleic acid testing, and implement them one by one.

In addition, Songjiang Power Supply Company's infrastructure, item management, production, regulation, and development strategy has jointly established the "Power Party Member Commando" to give full play to the role of party members' vanguard, and strictly implement the closed construction of engineering, acceptance and construction personnel strictly. Management, the whole process is stationed at the construction site, and the work of overhead lines, cables, power transformers, and self -healing joints in an orderly manner, which provides a strong technical guarantee for the smooth production of the substation. According to Zhang Yu, the project manager, the construction site of the substation strictly implements the "grid -based hierarchical management and control" to maximize the dense operation of personnel and avoid cross -operation of personnel from different participating units. At the same time, the technical uniforms of local construction personnel and local equipment manufacturers can be transferred as much as possible to reduce the risk of epidemic dissemination and ensure the steady progress of the project.

Text: Qu Hong Correspondent Shen Yanyi

Picture: Interview object provided

Edit: Ding Yijie Lu Yiyi Qin Tian

- END -

Shaowu City Natural Resources Bureau issued geological disasters Meteorological risk yellow warning

The Fujian Provincial Department of Natural Resources and Fujian Provincial Meteorological Administration jointly issued a geological disaster meteorological risk yellow warning at 17:35 on June 08, 2

Too strange!China Postal Savings Bank was stolen during the loss of savings cards, and the balance changed!

Recently, Mr. Deng, a citizen of Hengyang citizen, reported to the He Hotline for ...