up to date!10 of Guangzhou's undergoing subway line progress!

Author:Guangzhou, China Time:2022.06.14

What you care about

Guangzhou Metro is under construction line

There are new progress again!

Phase II of Line 13

Double -line penetration from Qingfeng to Huanggang

Recently, the "CG Qingfeng One" shield machine that shoulder the "CG Qingfeng One" shield machine that shoulders the tunnel of the shield tunnel on the right line of the Guangzhou Metro Line 3 of the Guangzhou Metro Line 13 came out of the north end of the Phoenix Station, marking the smoothness of the interval. Realize dual -line penetration.

At the same time, the rising shield tunnel from the rising sun to Qingfeng interval and the east extension of the east extension of the Metro Line 5 of the Metro Line No. 5 Shield Tunnel can also be fully connected.

As of now, the second phase of Line 13 (Chaoyang-Fish Bead): 49%of the Civil Construction Project has completed a total of 49%. Among the 23 stations, 3 have been capped, 19 are construction for civil construction, and 1 stations are prepared in the early stage; in the 23 sections, the five areas and the Huiqian parking lot in and out of the field have been connected. Preparation for preliminary preparation. Fish Parking Lot, Phoenix Parking Lot and Cover for civil construction.

The progress of the subway line is updated

Line 3 Dongyan section

(Panyu Plaza-Sea Piece)

A total of 68%of the civil engineering project was completed. Among the four stations, two were capped, and the remaining two were carried out in civil construction; one of the four sections had been connected, and the remaining 3 of the civil construction were carried out. Guangzhou New Town Parking Lot is prepared before construction.

East extension of Line 5

(Wen Chong-Huangpu Passenger Transport)

A total of 60%of the civil engineering project was completed. Among the 6 stations on the entire line, 3 stations have been capped and started mechanical and electrical construction, and the remaining 3 are carried out in civil construction; two of the 6 areas have been connected, 4 are carried out in civil construction; Essence

Phase 2 of Line 7

(University Town South-Northwest Water)

The cumulative civil engineering project was completed 73%. Among the 11 stations, four have been capped and started mechanical and electrical construction, and 7 of them are carried out in civil construction; 3 of the 11 areas have been connected, and 8 are carried out in civil construction. The Jiotang parking lot is carried out in civil construction.

Line 10

(Xizhen-Shipaiqiao)

Cumulative 44%of civil engineering projects. Among the 14 stations, 4 were capped, nine were carried out in civil construction, and the remaining 1 was prepared for preliminary preparations; 2 of the 14 sections had been connected, 4 were carried out in civil construction, and the rest were prepared in the early stage. The construction of the vehicle section of the Guangsteel New Town is carried out.

Line 11

(Railway Station-Pazhou-Railway Station)

The cumulative civil engineering project was completed 79%. Of the 32 stations, 2 have been opened, 14 have been capped, 15 are under construction, and 1 of the remaining one is prepared in the preliminary preparation. One of the 32 interval has been built and opened. Construction, the remaining 2 are prepared before construction. The construction of the Chisha vehicle section and the entry and exit section is carried out for civil construction.

Line 12

(Xunfenggang-University Town South)

Cumulative 44%of civil engineering projects. Among the 25 stations, 6 are capped, 18 are carried out in civil construction, and the remaining 1 is prepared for preliminary preparations. Among the 24 sections, 2 sections are connected, 12 are construction of civil construction, and the remaining preparations are carried out. The Tutou vehicle section and the university town south parking lot for civil construction.

Phase II Phase II

(Jiahe Wanggang-Guangzhou Railway Station)

A total of 33%of the civil engineering project was completed. Among the eight stations, the main structure of the two seats was capped, and the 4 seats were carried out in civil construction. The remaining two were prepared for preliminary preparations. Among the eight areas, the two had been connected.

Line 18

(冼 州-Guangzhou East Station)

The cumulative civil engineering project was completed by 9%. One station is prepared for preliminary preparations, and the construction of civil construction in one section is carried out.

Line Twenty -two Line Pass section

(Chen Tougang-Fangcun)

Cumulative civil engineering projects have completed a total of 21%. Four stations are undergoing civil construction; one of the four sections is carried out in civil construction, and the remaining 3 are prepared for preliminary preparations.

(Note: The name of the above stations is only the tentative of the project, and the standard station name shall be based on the approval of the municipal government.)

Edit | Huang Jialu

Responsible editor | 禤 Zhijie

School Division | Zeng Weilei

Source | Guangzhou Metro

- END -

Follow Eye Health on Eye Day

On June 5th, a optical testist was explaining the knowledge of eyeball structu...

The market value has gone back 66.8 billion a day!Rumors disturbing, what is the anxiety and challenge in Ningde Times?

While the business expansion, the Ningde era also faced issues in the first quarte...