After spending 220 million, some people actually "never passed the water" ...

Author:Global Times Time:2022.09.02

According to the problem clues reflected by the masses on the "Internet+Inspection" platform on the State Council, the 11th Inspection Group of the State Council's Ninth Supervision Inspection Team in Hunan Province, Hunan Province, and found that some rural drinking water projects lack feasible in the early stage of construction. Sexual arguments lack maintenance management after completion. Some villagers guard the tap water pipes, but there is no tap water available. Puyang City said it would take practical measures to ensure that rectification was in place.

The inspection team visited the villages such as Xiaxiangxiang Village, Tianbao Village, Dongsheng Village, Guanghua Village and other villages in the Tanxia Township of Puyang City. Visit more than 10 villagers randomly, they all said that there is no tap water available, drinking water or drinking well, or buying water or picking water from a distance.

A villager said that the tap water pipe was built a few years ago in the village, but the pipeline had been abandoned. In Tianbao Village, the inspection team saw that the equipment room with the "National Rural Drinking Water Safety Project" was already overgrown. In a villager's house in Dongsheng Village, the inspection team saw that the number of tap water that had been rusty was "0". The villagers of Guanghua Village reported that a set of water drinking projects had been built earlier, but they never passed the water.

The inspection team learned that since 2005, Puyang City has invested 220 million yuan in funds and 579 centralized water supply projects were built. While investing a lot of funds and material resources, some villagers are still in difficulty in drinking water safety. Some villagers still have to pick water a few kilometers away.

At present, the newly -built water supply projects since 2005, 28%of the operation is average, and 7%of operations are difficult to collect, and 5%are idle. The inspection team believes that the lack of feasibility demonstration in the early stage of the construction of local rural drinking water projects and lack of maintenance management after completion.

Puyang City said that it will take the opportunity of the State Council's overall inspection, make a reform of the problems discovered, and take practical measures to ensure that the rectification is in place. The water supply project of the countryside and the water supply project of Dongsheng Village is actively soliciting the opinions of the masses. All the needs of the masses will restore water supply. The water supply project of Tianbao Village, which has been scrapped, solicits the opinions of the masses again. If the masses do need it, they will be restarted or newly built to restore water supply.

Puyang City feedback to the inspection team will increase the safety rate of rural drinking water, and once again "look back" for the city's rural drinking water safety project, and will formulate a rectification plan for "one question, one measure, one responsible person", and actively raise rectification to rectify rectification. Fund, implement rectification time limit, in order to rectify and establish a long -term mechanism.

Source: Xinhua News Agency

- END -