Qiqihar Civil Aviation Road cross -line bridge project is expected to have traffic conditions at the end of October

Author:Heilongjiang Daily Time:2022.09.01

As one of the key projects of Heilongjiang Province, Qiqihar Civil Aviation Road cross -line bridge project project has always attracted much attention. At present, the project is in a comprehensive steps in construction, and it is expected to have traffic conditions at the end of October.

Cross -line bridge projects for civil aviation roads to accelerate construction progress

The reporter interviewed at the construction site and stood on the bridge. The entire bridge had emerged. It was like a "Wolong" extended from east to west. It was magnificent and spectacular. Entering the construction site, the operation scene was in full swing, and the workers performed their duties, and the work was progressing smoothly.

It is understood that at present, the anti -collision wall and mid -part wall on the main bridge are being poured. The total length is 1056 meters, and it has been completed for 420 meters. The concrete pavement on the west side bridge surface has been completed. The bridge on the east side is welding and laying steel mesh. After all the concrete is paved, the black asphalt pavement will be laid as a whole. It is expected to complete all project construction in mid -October. condition.

According to reports, Qiqihar's Civil Aviation Road cross -line bridge project west of Muhai Sea Street and dawn south street in the east, with a total length of 837.2 meters. Among them, the main bridge is 352 meters long, and the main body of the bridge across the iron line. After opening, it will effectively connect the central urban area of ​​Qiqihar City and the southeast region to comprehensively promote the integration of the production and urban area of ​​the strategic emerging industrial park and the city center area, and promote the deep integration of the integrated area of ​​Qiqihar's six districts to help the rejuvenation and development of the old industrial base in Northeast China Essence

Source: Lottery News

- END -

The custom -made high -speed EMU and comprehensive testing train of Yawan high -speed rail are offline in Qingdao

China Economic Net, August 5th (Reporter Tong Mingbiao) On August 5th, a high -spe...

Rural human settlement environment improvement points in Jiang'an District, Fuzhou

Placing Fuzhou, June 29th News Maintaining his own hygiene, striving to get points...