When can the Guanqiao Station of Guangzhou Metro Line 4 started?Guangzhou subway response

Author:Golden sheep net Time:2022.09.13

Guangzhou subway response: The preparation of relocation is being carried out, and the construction time is "currently unpredictable"

Xu Zhentian, a reporter from Yangcheng Evening News: Recently, some people reported that the Guangzhou Metro Line 4 has been opened for many years, but there are no signs of construction at Guanqiao Station in Panyu District. They are very concerned about when the station starts. The reporter learned that the relevant parties are currently carrying out the preparations for land acquisition and pipeline relocation, but the station has not yet been included in the recent construction plan.

"The Guanqiao Station of the Fogwin Intercity has basically been completed, and recently completed the cold and slippery test of the railway, but there are no signs of construction of the official bridge station of Metro Line 4." Bridge station, in addition, he often pays close attention to the construction of the station through the bidding documents. According to its reflection: "At the end of last year, I noticed that I went to the station to conduct the bidding of engineering supervision projects, but it was still not started until now."

Guanqiao Station is the reserved station of Line 4, and it is also a connection station of the Buddhist city. It is located in the newly built -to -Shijie area, adjacent to the Guangzhou Innovation Base of the Tsinghua Science and Technology Park. The Lotus Avenue of the Guanqiao Station and the planned road of the Guancheng Intercity Bridge, the south side is the substation of Line 4, and the surrounding area is mainly based on farmland, village and towns.

The bidding document revealed that Guanqiao Station is an elevated two -story side stations. The total outsourcing of the station is 125 meters long and the total construction area is about 8964.125 square meters. After the Guanqiao Station was opened to traffic, Guangzhou citizens took Metro Line 4 and went to Guanqiao to transfer to Foshan Intercity. It was convenient to travel to and from Foshan or Dongguan.

The reporter sorted out and found that in May 2014, the Guangzhou Development and Reform Commission agreed to the "Research Report on the Feasibility Research Research Research Research Research Research Research on the Guanqiao Station of Guangzhou Rail Transit Line 4". Capital accounts for 40%of total investment. However, in April this year, the relevant bidding documents of the Guanqiao Station project were mentioned that the construction funds came from the government to raise funds at 100%.

In September 2020, the Guangzhou Metro publicly responded to the construction of Guanqiao Station: "According to the preliminary planning period, it is planned to start construction in the second half of 2021, and strive to complete the construction task by the end of 2024." However, the construction of the construction was expected to fail that year failed to fail that year. accomplish. In October 2021, the Guangzhou Metro issued the bidding announcement of the engineering supervision service project of the station, but in March this year the bidding ended for some reason. In May this year, the project launched the bidding and completed the publicity of the bid candidate.

When can Guanqiao Station start? The Panyu District Development and Reform Bureau of Guangzhou City responded that the Foguan Intercity Railway has been basically completed and is currently in the acceptance stage. The official bridge station of Guangzhou Metro Line 4 belongs to the reserved elevated station and has not yet been included in the recent construction plan. "Because the planning and construction authority of rail transit is not at the level of the district, relevant districts will cooperate with the progress of the progress of the Metro Guanqiao Station and the intercity construction of the Buddhist and Wuan to meet the travel needs of surrounding residents."

On September 7, the relevant person in charge of Guangzhou Metro revealed to reporters that the bidding work has been completed, and the subway group is cooperating with local government departments to carry out preliminary preparations such as land acquisition and pipeline relocation. As for the construction and opening time of the station, the person in charge said that "it is not expected."

- END -