Fight on the front line | On the first day of resumption, 86 workers "returned to the team"
Author:Chuanguan News Time:2022.09.14
Chuanguan News reporter Peng Yan Zhang Minghai
Project business card
Tianfu Science and Technology Park, with a total investment of 2.15 billion yuan, covers an area of more than 100 acres. It is expected to be delivered at the end of June 2023. The project was designed by the famous Hong Kong designer Yan Xunqi team, which aims to create a "Hong Kong flavor" professional creative space and strive to build an internationally renowned innovation and entrepreneurial center.

Project aerial map. China Construction Three Bureau Photo Conferry
"Hurry up and get out of the analysis of the schedule as soon as possible!" On September 12, the first day of the Tianfu New District resumed work. At 7 am, Wang Long, who successfully returned to the team, walked into the construction project department of Tianfu Science and Technology Park 1 in Xinglong Lake.
As a technician of the project department, Wang Long's office was prevented and controlled by the epidemic. As soon as he received a notice of resumption, he came early in the morning to become the first person to return to the job that day.
Tang Bing, the person in charge of the construction unit of the construction unit, told reporters that on the first day of the resumption of work, the project department urgently convened 86 workers to "return to the team", and they continued to step up the construction with the 244 staff members who were left behind.
Half of the soldiers achieve "Mange" combat effectiveness
Since the epidemic, the combat effectiveness of the Tianfu Science and Innovation Park Land Construction Project has been reduced by half: more than 300 workers who do not live in the living area of the project department cannot enter the field, and only 244 people who live in the construction site have been left behind.
In less than half of the manpower, will the project continue to advance?
"Under the premise of doing a good job of epidemic prevention, we started closed -loop management." Tang Bing introduced that after the epidemic, the project department started a closed -loop management plan. In addition to the essential masks and disinfection, antigen test reagents are also prepared. In terms of living materials, vegetables, fruits, and meat products have been reserved for 15 days.
What should I do? The project department re -created the process. The project managers pulled out the list, position, and type of work of the guards, and corresponding to the current construction progress to reorganize the construction process. Dragon welding, steel structure reconstruction, ceiling construction, partitional installation, masonry material transportation ... Each construction content is refined to the head, refined to the date.
"Construction period, delay." Zhu Xueqing, director of the project comprehensive office, introduced that the Tianfu Science and Technology Park project led by the well -known architectural designer Yan Xunqi team in Hong Kong, focusing on cultural creativity, fintech, and intelligent hardware. Hong Kong youth talents, which are innovative and entrepreneurship, provide "Hong Kong flavor" to provide "Hong Kong -flavored" professional creative space.
Workers and building materials have begun to "return to the team"
"Repeated work!" In the early morning of September 12, the notice of the orderly restoration of production and living order in Tianfu New District, Tang Bing's exhaustion disappeared in an instant, bounced from the marching bed, and called and sent a message one by one.
Who do you call the phone? Sichuan Xingrui Hao Trading Company, Taiwan Glass Chengdu Glass Company, Chengdu Sunshine Aluminum Products Company ... All are building materials suppliers. "Immediately prepare for supply, and make up for all the delay the previous day!" This night, the supply manufacturer prepared the materials overnight.
The resumption notice was also issued quickly. In the early morning of September 12, there were 86 people who took the initiative to work like Wang Long. In the afternoon of the same day, three large trucks with 900 square meters of curtain wall glass, 30 -ton aluminum profiles, and 32 -ton pipelines also entered the construction site.
Getting the work period, it is necessary to maintain quality. At present, the main structure of the project has been capped, and the installation part is basically completed.
On September 12, the reporter saw at the scene that one -third of the outer wall where the workers were under construction had put on the "clothes" -mids curtain wall. "In fact, there is a layer of aluminum decoration outside the glass curtain wall. At present, we are also undergoing simultaneous construction."
On September 13, all the remaining home workers arrived at the job, and the construction site was even more lively.
"The project will be completed and delivered in June next year." Zhu Xueqing said that the "Hong Kong style" elements of Tianfu Science and Technology Park will not only become "Internet celebrity punching land" in the future, but also strive to build an internationally renowned innovation and entrepreneurial center.
- END -
Watching Rizhao Development 丨 As of June 30, Rizhao Automobile Consumption Tounitan issued cumulative sales of 412 million yuan
Qilu.com · Lightning News, July 29th News On the afternoon of July 29, the Rizhao...
Holding the "new farm tools" farmers in Chengdu Dayi County to cultivate thousands of acres of "smart fields"
Cover reporter Liu Xuqiang Zhou Bin Intern Wang Daohan Shi Yuxin Photography Repo...