After the typhoon "plum blossom", all Zhejiang power supply has been restored

Author:Zhejiang Daily Time:2022.09.15

Zhejiang News Client reporter Hu Jingyi Correspondent Chen Lisha Zhang Zhenghua

On September 14, near a farmland in Beitang Village, Linhai City, the medium -phase melting wire of a base rod was blown off by the wind. State Grid Lingshi Power Supply Company Taozheng Power Supply Institute for the Restaurant Persons' repair on the 10 kV Dongyang L183 is eliminated to ensure the stable power supply of residents of 9 villages. Zhejiang News Client Correspondent Cheng Mengzhang Photo

On the 13-15, due to the influence of the typhoon "plum blossom", some electric equipment in Ningbo, Zhoushan and other places in Zhejiang was damaged, and the State Grid Zhejiang Power made every effort to carry out power rescue disaster relief. As of now, all the province's affected power supply has been restored.

Affected by heavy rains, there are waterlogging in some areas of Ningbo and Zhoushan, which has increased the difficulty of rescue and disaster relief. "The wind stops, the water retreats, the people enter, and the power through the power." Under the premise of ensuring safety, the State Grid Zhejiang Power Safety and Power Repair personnel in order to do a good job of post -disaster repair and restoration. It is understood that the typhoon caused a total of about 520,000 users in Zhejiang. As of 17 pm on the 15th, the affected users of the province had resumed power supply.

On September 14, the power supply company of Luqiao District, Taizhou City, State Grid eliminated the hidden dangers of 10 kV lines in Tongyu Street to ensure that more than 380 residents used electricity. Zhejiang News Client Correspondent Lu Weinan Photo

In Zhoushan, the State Grid Zhoushan Power Supply Company will build a disaster prevention control platform for islands, and the panoramic view presents the situation of "people, wind, water, disaster, and things" to achieve the command of typhoons and electricity.

Strengthen the monitoring of submarine cables locally, start a strong typhoon weather, sea cable prevention external emergency response, and send members to the Maritime Emergency Command Center to implement a safety control of more than 2 kilometers for 7461 returning to Hong Kong. Emergency trailer key management controlled anchor loss area.

At 20 o'clock on the 14th, the Lunnan Power Supply Company of Beilun District, Ningbo City, Ningbo City, found that the wire 4 and 5 of the Yongan Line Yuwangling Tunnel Branch were scratched by the wind. Danger.

To this end, the Lunnan Power Supply Institute urgently arranged personnel to simply deal with the lines in the storm to eliminate hidden dangers. After the wind stops, the power employees will be carried out for the first time to ensure that the company's normal production and residents' normal lives the next day. In Ningbo, there were 3899 people in the local power repair team.

On the evening of September 13th, employees of the Power Supply Company of the Lizhou District of Ningbo City, State Grid, took storms to eliminate the power supply equipment affected by typhoons to ensure the safety of more than 620 residents of the surrounding households. Photo by Hong Haozhe, a correspondent of Zhejiang News Client

It is reported that the State Grid Zhejiang Electric Power launched a typhoon prevention level Ⅰ response. The province's preparation teams were 1,333 and 1,467 special vehicles, and various types of emergency equipment were 251,000 units. Power grid employees have in -depth flood prevention and rescue lines, comprehensively carry out typhoons, and have accumulated a total of 1,2289 special patrol staff, 4,597 vehicles, 2125 inspection substations, 3507 transmission lines, 2161 distribution lines, and 24,519 Taiwan districts.

- END -

The first "zero -plan power outage" demonstration area of Fucheng was completed

In the citizen's impression, the power supply department often issues a power outage announcement, and plans to perform power outages or replacement of poles such as power outages or replacement of po...