To deal with the typhoon "plum blossom", Shanghai set a new record for the number of typhoon transfer

Author:Xinmin Evening News Time:2022.09.15

In the process of "plum blossoms", Shanghai has shifted a total of 426,000 people, setting a new record for the number of typhoons. Among them, Pudong New District should transfer the number and actual transfer of 147,000 people, which is the first district in the city. Jinshan District plans to transfer and evacuate 17,000 people, and basically completed the transfer and evacuation at 15:00 on the day. After the Typhoon Orange Warning was issued yesterday, Fengxian District began to withdraw from 19084 people in the construction site, the dangerous shed simple house, the old house, and the operation of the pond. At 18:00 that night, all the resettlement staff evacuated.

Fengxian

More than 6,000 people on the night to defend the "plum blossom"

More than a hundred sets of anti -water "artifacts" see effect

Driving the wiper to the maximum, and the front windshield is still blurred; the vehicle is driving on the coastal highway, and it is shook by the wind; as long as the car is in the car, it will be soaked immediately ... Yesterday, the reporter drove in the Fengxian Bay tourist area yesterday. I felt the powerful power of the typhoon directly. From the early morning of this morning, the roads and trees in Fengxian District fell. With the efforts of more than 6,000 flood control personnel overnight, they finally spent the typhoon struck.

The smart screen system of the Flood Control Command in Fengxian District. Figure Conferry at the News Office of Fengxian District (the same below)

Personnel transfer

At the placement point of the Gulf City dormitory in Fengxian Bay Tourism Zone, the reporter saw 27 resettlement staff from nearby sea pond planting and breeding enterprises. Each single room can accommodate up to 6 people and is equipped with an independent bathroom. The staff distributed living materials such as bedding, toilet paper, drinking water and food. An old man who worked in a nearby plant told reporters that she was evacuated here for the fifth time and had "familiarity with the door."

Bund video

In Fengxian May 4th area, the police of the May 4th Police Station notified the flood control platform in the area under the jurisdiction to assist the growers to make windproof reinforcement on the greenhouse and mobilize the vegetable farmers to transfer to the resettlement point. In the jurisdiction of the Fengpu Police Station, a total of nearly 1,400 construction workers in the construction site and the industrial development zone of the Youth Activity Center were resettled in time.

Dangerous disposal

From the middle of the night yesterday, a total of 6585 emergency teams in Fengxian District entered a state of war and inspected all night.

According to statistics, as of this morning, due to the influence of typhoons, 38 water accumulated in Fengxian Road in a short time, instant water accumulation in 10 communities, and 1,163 trees fell down. All have been dealt with. The May 4th area caused a power interruption due to the inverted trees, which affected about 1,000 residents of about 1,000 residents in two residential communities. At present, it has been restored to power supply. In terms of agriculture, farmland was affected by 6888.3 acres; the greenhouse was damaged by 852.4 acres, with a total of 1120 units; 39.5 acres of ponds and damage to ponds. Total 7.148 million yuan. According to reports, because the typhoon strikes in September, it is not the peak season of fruit and vegetable crops in Fengxian area. Compared with the previous years of the typhoon season, it has less losses.

Flood prevention personnel in Fengxian District are cleaning up the pouring trees

At 5 am this morning, as the typhoon was away, the wind and rain in Fengxian District gradually died. Xu Jianbing, a staff member of the Flood Control Office of Fengxian District, told reporters that from the results of the one -night inspection of the duty, the most problem was the pour and water of the trees. The guards on duty in various regions are not intermittently inspected. Once the trees are found to be cleaned up in time, and the greening department is notified for subsequent disposal. In addition, the 105 sets of waterlogging water accumulation monitoring equipment installed by Fengxian District earlier this year played a role. Once the accumulated water exceeds the alert level, the system will report to the alarm. The position is basically dealt with in time.

At 6 am this morning, the Fengxian District Meteorological Orange update orange early warning signal was a typhoon blue warning signal. The district flood prevention headquarters decided to adjust the II response of the flood prevention platform to the flood prevention platform IV level response. At present, Fengxian District has started the resettlement personnel to return to work.

Jinshan

"The residents have been resettled, and the home must be guarded."

Petrochemical Street's residential district staff to guard the community all night

At noon yesterday, the wind and rain were overwhelmed. Typhoon "Plum Blossoms" is coming again this year. Jinshan District, located on the banks of Hangzhou Bay, is holding the work of safeguarding the transfer of personnel. The personnel have shifted, what about their home? "The residents are settled, and the resident's home must also guard it. When the typhoon passes, when the residents return, it is still a safe place." This is the answer given by Xia Lei, deputy secretary of the Party Working Committee of the Petrochemical Street.

The reporter spent a sleepless night with more than 20 "home nursing homes" staff in the three groups of flood prevention resistance in Dongcun District, Petrochemical Street, and more than 20 "home nursing homes", including Xia Lei.

Police strengthen inspections. Jinshan Public Security Pictures

Hundred -year -old elderly transfer safe transfer

It is said that it is a "command room", which is actually a small room next to the gate of the community. A monitoring screen is installed in the room. You can clearly see every move in front of the gate. The gate has been closed, and the two security guards guard the door in the wind and rain.

Bund video

In the evening, the box lunch arrived. Deng Haibin, secretary of the General Party Branch of the Dongcun Resident District, immediately told the social workers to Qiu Yi and Shi Shiwei, and first sent the box lunch to the three oldest residents of Jinwei and Fang Xiaomei, a 102 -year -old.

Fang Xiaomei's old house has a history of more than 100 years. The terrain is very low, the water is easy to accumulate, and the hygiene conditions are poor, but the old man is difficult to leave, and he always refuses to move away. Four children can only take turns to take care of her. This evacuation, the neighborhood committee considered that she was so old and was not suitable for centralized resettlement points. Therefore, Deng Haibin booked the hotel in advance, allowing the elderly's daughter, Ms. Zhou and the elderly to live together, and arranged food until the typhoon passed.

Reserved "office workers" and other "office workers"

The three groups of Jinwei and Haiguang Group in the residential area of ​​Dongcun have a long time and fragile structure. "Unfortunately, when you encounter working days, most residents work in the unit." Xia Lei said, "Considering the reality, after 3 pm, we basically closed the entire community. At the same time After the residents arrive at home, simply pack their luggage and send them to the resettlement point. "

117 calls in half an hour

At about 8 o'clock that night, in another small room next to the command room, the six cadres of the commissions were busy calling -before the typhoon came, 156 people touched the resettlement personnel, but the resettlement point of the rotation of Jinshan District Only 39 people were placed, and where did 117 people go? "We checked it carefully and contacted 117 people in more than half an hour." Deng Haibin said carefully, "Mastering their movements can make people feel at ease."

According to reports, a total of 929 people in the residential area of ​​Dongcun should be evacuated, of which the three groups of Jinwei were 747 and 182 in the eight groups of Haiguang. There were 156 places in the two places, and 50 people were actually resettled yesterday. Others have invested in their own friends or leased hotels by themselves.

On the night of the "home nursing home"

Xia Lei introduced that after the personnel are resettled and the area is closed, the staff will protect the safety of the community overnight to prevent other personnel from entering the community. On the other hand, they will often patrol at night to see where the house is prone to damage and whether the sewage is in sewage. Plum overflow and so on. "In the end, there is another job to do. Our hydropower workers need to further inspect the safety of the existing houses of residents. Only when these houses are safe, they can let residents go home." He emphasized.

Hong Kong

Patrol of 24 hours along the seaside line

Stormy and rainless at the outpost, flood control platform to eliminate dangerous situation

Located on the southeast coastal port, it is located at the intersection of Hangzhou Bay and the Yangtze River mouth. Min Chuntian, a flood prevention cadre, did not sleep overnight. He was on duty at the Flood Control Command Center in the Lingang New Area. Min Chuntian keeps an eye on the real -time path map of the typhoon on the screen of the city Yun University. Wait for the staff of the functional departments to ensure that the danger is excluded as soon as possible.

Seal patrol and persuasion

Last night, more than 110 people insisted on their posts in the management committee of the Lingang New Terminal District, and 197 people in the Nanhui New Town Community Community also sent a duty class in the job. Wang Zhiqiang, a member of the comprehensive law enforcement brigade patrolling by the seawall, told reporters that all the embankments from Luchao Port Seafood Market to Nanhui Mouth Observation Sea Park were closed. Permanently return.

The reporter learned from the Lingang New Town Police Station that the coastline of the Lingang area was 30 kilometers. They were equipped with 10 policemen and 50 auxiliary police officers along the seaside line.

Construction worker transfer

According to statistics, there are 367 construction sites under construction in the new area of ​​Lingang, 56045 on -site personnel, 5,3719 personnel themselves, and 2,326 resettlement personnel are required.

According to Yu Junbin, the project manager of the Youth Activity Center of the China Construction Eighth Bureau, the staff went to the resettlement site in advance the night before; yesterday morning, the construction site staff was inspected by the nucleic acid; In less than 2 hours, the 284 people in the project were all transferred.

Bund video

It is reported that a total of 5 buildings in Hong Kong City Square are set up as resettlement points, and the second to 5th floor of each building is vacant. As a living area of ​​transferred staff, about 2,500 people can be accommodated. The reporter saw that the order at the scene was well -organized. According to the staff's guidance, the workers measured their body temperature and disinfection, and entered the rest area. In the resettlement point warehouse, instant noodles, mineral water and other supplies are neatly placed.

Pre -descending inland water level

On the coast of Linkang, the water level of the inland and the sea has become the key to flood prevention. According to the unified scheduling in the city, through the tidal forecast, the water level monitoring of the inland river, and the real -time monitoring of the rainfall, the pre -reduced water level in the Hong Kong Hong Kong will free up enough space to save rainwater to avoid urban waterlogging.

"Plum Blossoms" landed, and the feelings of Lingang were obvious. Outside the window, the wind was tainted, the rainstorm was like a fence, and the fences and trees were scratched. Subsequently, emergency rescue vehicles arrived in time to ensure that transportation was not affected. This morning, with the typhoon gradually away, the weather in the new area of ​​Lingang gradually returned to the same way, and the people who persisted all night were relieved.

Songjiang

No one is settled at the construction site without one person

24,000 people evacuated and transferred

The center of Typhoon "Plum Blossom" No. 12 this year has landed again on the coast of Fengxian in Shanghai this morning and moved into Jiangsu Province.

The flood prevention site of Shihuangdang Town. Interviewee confessed (the same below)

For many people, this is destined to sleep overnight. In order to face the "plum blossoms", since September 12, various departments and units of Songjiang have strictly implemented the 24 -hour duty system for leadership. A total of more than 24,000 people who need to evacuate the dangerous houses, construction sites, and temporary sheds in the district, and the transfer was completed at 23 pm on the 14th. All transfer personnel have implemented nucleic acid testing, and 249 transfer and resettlement points have implemented the prevention and control of the epidemic.

The head of Pujiang is located in Shidang Town, Songjiang District. This is zero kilometers of the Huangpu River. The oblique Tangjiang River, Yuanluo, and Hengshujing, which are winding from Jiangsu and Zhejiang, gathered here. Yesterday afternoon, the storm was getting stronger. "We are on the edge of the Huangpu River, which is affected by the wind." Shen Jiaxi, director of the Agricultural Office of Shi Dangtang Town, told reporters that in the summer of previous years, such as the typhoon "Lichima" and "Fireworks", such as the typhoon Essence "In the face of the typhoon 'plum blossoms' this year, we have also taken preventive measures. On the one hand, we strengthened inspections, dredging the gutter and reinforced road trees, etc.; Between 5, flood control materials and equipment such as pump pumps are ready. "

According to statistics, there are 14 points in Shi Dangtang Town, and 1051 people need to transfer and resettle. Some of these points are some of the rural areas scattered in rural houses, and the other part is derived from the construction site under construction. "In recent years, with the centralized resettlement and reconstruction of the villagers' housing, fewer and fewer villagers need to be transferred." Shen Jiaxi introduced, "This year, the main focus of our prevention of flood prevention in Taiwan is the project site. There are three construction sites and more than 560 people need to transfer and resettle. "

The reporter learned that Shihuang Town Cultural Activity Center, Village Elderly Activity Room, and some farmhouses were set up as temporary resettlement points. Among them, the cultural activity center can accept 600 people to check in. "When transferring resettlement, we also strictly implement the requirements for epidemic prevention and do a good job of coding and temperature measurement." Shen Jiaxi introduced that the cultural activity center also deliberately divided into a relatively independent space on the first floor of the main building, the second floor of the main building, and the auxiliary building, and accepted separately, respectively, and accepted separately. Three construction sites of the Songjiang section construction project of the Shanghai -Soviet Lake Railway. Flood prevention materials and logistics support in the resettlement point, including mineral water, instant noodles and other foods, daily necessities such as towels and quilts are ready.

Yongfeng Street Flood Prevention Scenes

At the same time, in Yongfeng Street, which is adjacent to Shihu, transfer resettlement work is also stepping up.

On September 13, the work of the flood prevention platform was deployed in advance; the early warning pre -notice was received by the warning upgrade at 2:30 pm on September 14th; the resettlement preparation was made at 4 pm ... the various tasks were carried out in an orderly manner.

Hu Bin, director of Yongfeng Street Flood Control Office, told reporters that the old dangerous house has always been the focus of the typhoon weather. Cangcheng Historical and Cultural Standard Area is located in the streets of the street. In the old houses near Zhongshan West Road and Xiunan Street, a small number of residents also lived sporadically. "We have confirmed the number of people who need to transfer and resettlement with the local neighborhood committee. In general, with the experience of preventing flood prevention in the past years, residents have cooperated more this year. More smooth. "

There are also many construction sites in Yongfeng Street. As the typhoon approached, the front streets have been contacted in the construction site of the construction site. "In order to ensure safety, we require that after the secondary response is started, all construction sites will not leave one person and all employees withdraw from. The person in charge of the construction site is implemented and resettled. Hu Bin told reporters that many construction sites have been looking for hotel arrangements to check in this year, and there are more than 400 people in charge of the street. In the placement point, epidemic prevention measures such as the place code and digital sentinel have been ready.

When the typhoon was heavy in the heavy rain in previous years, some of the streets had a long period of water accumulation. In the early stage of transformation, inspection of water accumulation points, and reducing the water level of the inland river ... "We would rather" ten defense and nine empty ", and we must try our best to ensure the safety of the lives and property of the people." Hu Bin said.

The reporter was informed that as of 8 am, heavy rainy weather and 7-9 winds in Songjiang. The highest water level of Mishuang Station is 4.62 meters, the water level is 0.82 meters, and the water level is generally controllable. There are 1 intersection of water in the region, the sidewalk trees fall or break 18, the vegetables and vegetables are overwhelmed by 120 acres, and the greenhouse is damaged by 340 units. The rest of the situation is normal.

Typhoon "Plum Blossom" transit

Early peak traffic is smooth and orderly

The police of the Corps viaders guided traffic on elevated roads. Police drawing

Affected by the typhoon "plum blossoms", the city of this city fell heavy rain last morning. The reporter learned from the Municipal Public Security Bureau in the morning that in order to ensure the order of traffic in the early morning of this morning, the Shanghai police continued to prevent high -level social prevention and controlling service, carry out street patrol, hidden danger investigation, traffic dredging and emergency response, and fully ensure the safe and orderly operation of the city.

In the early morning of this morning, the city's traffic police departments were full of duty. Each branch of various bureaus was superimposed to the input authorities and police station police forces to reinforce traffic to guide, and to do their best to do a good job of traffic management and strictness. Traffic safety.

During the early peak, the north and south elevated north to the South Guangzhong Road to the Xinzha Road, the Yan'an Elevated West to the Donghua Mountain Road to the Yandong Lixing section, and the south of the Huimin viaduct to the north Liuzhou Road to the Cixi Lizi section. For a long time and large -scale congestion, the city's road traffic is generally smooth and orderly.

As of now, the city's water -based water -based water points have not produced traffic travel due to large -scale water accumulation. Affected by the suspension of typhoons and rainfall, many citizens traveled early. Therefore, today's early peaks have been advanced, and the city's traffic accidents increase by about 20 % compared with daily. From 6 o'clock last night to 6:00 today, the total number of 110 alarms rose, of which the city's trees fell down 214. At present, the relevant police conditions have been properly disposed of, and no casualties caused by typhoons have not occurred. Due to the suspension of all ferries, during the early peak peak, the traffic police department opened a non -motorized lane on the upper floor of the Fuxing Road Tunnel for passing. It also adopted a police car to escort non -motor vehicle concentration to the river on the Dalian Road Tunnel to ensure that the citizens crossed the river safely and convenient. At 6:30 in the morning, Hongkou Police has begun to guide non -motor vehicles that need to be accepted in the Dalian Road Tunnel. After the backlog of the vehicle to a certain degree, the traffic police conduct temporary traffic control on motor vehicles. Lead non -motorized fleets to cross the river from the tunnel at a safe speed of 20 kilometers per hour.

Reporter Pan Dafeng special correspondent Li Hui

Xinmin Eye Studio

Author | Li Yineng, Yang Huan Yang Jie Pan Gaofeng

Special correspondent | Li Hui

Edit | Gu Yingying

- END -

The international media have focused on the first anniversary of the U.S. military withdrawn from Afghanistan. They believe that the negative impact of the US military's invasion of Afghanistan is still continuing, and the Ministry of Foreign Affairs responds

On August 19, 2022, the Ministry of Foreign Affairs spokesman Wang Wenbin presided...

Beijing: Building and operating electric vehicle public charging facilities will be subsidized

Building and operating electric vehicle public charging facilities can apply for funding subsidies. In order to promote the charging facility network of mainly charging in residential and office land