Substation of substation, renovation and transformation to relieve the people's worries

Author:Fuzhou News Network Time:2022.09.17

1663391890250.png

1663391909446.png

Recently, after a tense and orderly debugging, the 5 -month -old Mayang Mayang 110 kV transformation station No. 2 Main Transformation Project has successfully launched the power delivery project, laying a solid foundation for residents to welcome the normal electricity use during the peak.

It is reported that Ma Yang's 110 kV substation was completed and put into operation in 2006, mainly to bear the power supply tasks in the urban area. In recent years, with the rapid development of Yongtai's economy, electricity load has continued to rise, and the maximum load rate of the main change is nearly 85%. Ma Yangcai's main change project not only effectively alleviates the tension of electricity consumption in the area, but also greatly improves the power quality and power supply reliability of the supply area, providing a solid guarantee for local residents' living electricity.

In order to ensure the smooth delivery of the project, Fuzhou Electricity Supervision and Consulting Co., Ltd., which belongs to Fujian Rongneng Electric Group Co., Ltd., overcomes many problems such as tight construction periods and tasks caused by the epidemic of new crown pneumonia. Material entry, strictly control the design drawings, and grasp the "four strictness" effects of technical specifications, implement the standardized supervision of the "one table, one card, one card, one list, one list", and the performance requirements of "plans, on -site, instructions, and information" will run through the entire process of supervision. Essence Urges the existing problems to urge the construction project department to closed the rectification to effectively solve the various safety hazards in construction. After more than 150 days and nights, the supervisors were accompanied by the gray soil, accompanied by the wind and rain, and completed the supervision work with hard -working sweat and standard supervision style.

In recent years, Fujian Rongneng Electric Group Co., Ltd. has strengthened the two -way integration of party building and business, the internal connection between party building work and business work, deeply cultivating the "party building+N" model, integrating party building projects into the key tasks of the year, comprehensively improved, and strive to build The core team of "knowledge type, innovation, and skill type" independent supervision has continuously improved the support ability and service level of infrastructure projects, and provided strong power guarantees for residents to produce and live electricity with practical actions.

- END -

Waiting for a "life -saving heart" in Guangzhou, the 11 -year -old heart failure boy is reborn

Jimu Journalist Liu Xun Wang ChenxiPhotography reporter Wang YongshengVideo editin...

Star night aid, target Tibet!They are coming from all directions

As a hospital in Tibet, we have no loan at this special time home to support! Wu Y...