Henan Legal System "Henan Legal System Daily" was founded in 1984 and was sponsored by Henan Daily Newspaper Group. It is the only legal newspapers for the province's province that the Henan Provincial Party Committee and the Provincial Government's clear positioning. 513 original content public account,

On September 19, the reporter learned from Zhengzhou thermal Group that recently, Zhengzhou thermal Group issued the "2022-2023 Heating During Heating Schedule", marking the full development of the heating guarantee work this winter and tomorrow.

Zhengzhou City heating scale

Stable in the forefront of the national heating enterprise

It is understood that in 2022, the total area of ​​centralized heating in Zhengzhou will exceed 200 million square meters. It is expected that the new heating area is 9.57 million square meters, and the total heating area is nearly 120 million square meters. Enterprise at the forefront.

At the same time, the situation of the heat source this winter is severe. In the case of no new thermal source projects, the contradiction between supply and demand of the heat source is prominent, and the tension of the heat source has intensified. In this context, Zhengzhou thermal force group coordinates the multi -thermal source configuration and the "one city, one network" layout, and combines the construction of the user thermal load and the construction of the key road section. Scientifically compiled a scheduling scheme that meets the heating needs of our city.

Liyang was first included in the scope of central heating

This year, the Puyang area was included in the scope of central heating for the first time. It simulated the operating conditions of the research operation, and implemented the transformation of the facilities of the partial pressure station to solve the problem of the heat source and the user.

Plan for new construction network 60 kilometers this year

The key municipal pipeline network construction project is the key to this winter heating protection. It not only affects the full play of thermal source capacity, but also helps optimize the overall pipe network layout and improve the safety of heating. This year, Zhengzhou thermal Group made every effort to promote the progress of the new heating pipe network. It plans to build a new management network of 60 kilometers and strive to open up the second route of heat transfusion in the southeast and west of our city.

From 2019-2021, Zhengzhou thermal Group has completed a total of 536 road sections, 120.99 kilometers (including one network and a branch network) old pipe network reconstruction, which greatly eliminates hidden dangers of the pipe network and improves the safety of the pipeline network. This year, Zhengzhou thermal force investigated the old pipe network of the city, and the hidden dangers should be changed to the renovation of the old pipe network through the three roads, university roads, Xinghua Street, and epidemic prevention roads.

Over the years, Zhengzhou thermal Group has insisted on the implementation of water maintenance and regular cold -state operation on the city's heating pipe network in the non -heating period. state. This year, it has been carried out in 5 times, and 44 leakage points have been treated.

According to the heating plan, Zhengzhou thermal Group is expected to complete various heating preparations in late October, and the heating system has operating conditions. On November 1st, the city's pipeline network started cold operation. On November 7, the heat sources were heated, and the pipe network began to rise to ensure that the user room temperature on November 15 was reached.

Warm reminder At present, the peak season of centralized heating into the installation and grid -connected acceptance, users can "one stop" in Zhengzhou's official WeChat public account for pre -reporting counseling, online installation, user recruitment, and inquiry inquiry inquiries in query inquiries. Link. You can do it without meeting the whole journey. Users who need to archive can also enjoy free mailing services. In addition, Zhengzhou thermal force also introduced differentiated design counseling to guide users to construct in accordance with design drawings and related specifications to avoid unnecessary errors during construction. The installation system further streamlined the acceptance procedures, optimized the opening link, reduced the time limit of the processing time, and the acceptance time limit was reduced from the original two working days to 1.5 working days. At present, the project design drawing design counseling, on -site counseling contact form, and the acceptance application application can be implemented through the "Zhengzhou thermal" WeChat public account. Design coaching opinions, on -site counseling opinions, acceptance rectification opinions can also be downloaded through the WeChat public account installation system to download the electronic version of the electronic version. document.

Henan Political and Law System 6 people won the title

Mayor Luoyang appeared in court! Zhengzhou government website platform is attacked! Henan Police notified 10 typical cases of Henan issued important announcements! From October 1st, private cars and motorcycle inspection cycles are adjusted! Source: Zhengzhou Release, Zhengzhou Daily Editor: Yang Shufang

"Henan Legal Daily WeChat Video No." content is recommended to poke at the Henan Legal Daily

- END -

Tibetan corpse, abduction ... chasing this drama and seeing neighbors are afraid

This is an ordinary and peaceful morning.In the Lan Lan Garden Community, Yang Yua...

Tibet will arrange 70 million yuan subsidy funds to help enterprises to benefit the people from seven aspects to promote consumption

In order to implement the central and autonomous regions' decision -making and dep...