Three months will achieve "Dentong"!Wuhan two billion project supporting projects ushered in the latest progress

Author:Nine Pai News Time:2022.09.25

【Source: Voice of Hubei】

Today (September 25), AVIC lithium battery and Xiaopeng Automobile 110kV special substation were built by the China Communications Second Aviation Bureau. "".

[Recording report] Three months to achieve "electricity"! Wuhan two tens of billions of project supporting projects ushered in the latest progress .mp3 2:24

AVIC Lithium Electric Wuhan Production Base Transformation Station

The project is located in the Wuhan Economic and Technological Development Zone, with a total length of 9.6 kilometers. The main construction content is civil construction channels, line laying, mechanical and electrical installation and pipeline relocation. According to Zhifeng, the production manager of AVIC Lithium Power and Xiaopeng Automobile 110kV of Xiaopeng Automobile, the CCCC Secondary Aviation Bureau introduced that the project has passed through 8 traffic intersections along the project, 16 unmn -traffic intersections, with many underground pipes and dense pipeline distribution. In order to protect the existing pipelines, the project increases the investment of detection equipment and personnel, completes the pipeline inspection and resolution, so that the pipeline of "invisible" pipelines can be visualized.

"Before we construction, we will use metal detectors, waveform detectors, etc. to detect all pipelines, find out their approximate positions, and then find it by manually excavating. After digging out Protect and then excavate mechanical excavation, so that all the pipelines that pass will not cause damage. "

Tube embedded pipeline construction

Workers are under construction

In addition, in order to successfully wear about 100 meters wide, the project department has adopted river steel custody through the shape of a semi -arc to pass through the riverbed, and combines the terrain conditions to select the non -excavated level weighing 600 tons of non -excavation levels. Construction of directional diamonds. Zhi Gao Feng introduced that this method is both economical and environmentally friendly.

"If the traditional method is adopted, it will be slower for at least a month, and it will be a bit more economically exceeded. (Traditional method) has a mud emissions, which is serious to the river pollution."

It is understood that the project from construction to stable sequences, only 90 days of efficiently achieve the entire line of "electricity". The project completion and application of the project is of great significance to promote the implementation of the two tens of billions of projects in the Wuhan production base of AVIC Lithium Corporation. "Car Valley", "Power Car Valley", "Vitality Car Valley" and "Charming Car Valley" provide important support. Li Ming, the person in charge of the Lithium Power and Xiaopeng Automobile 110kV Entering Project of CCCC Secondary Airlines Bureau:

"We refer to the projects of the same type and size in the past. The construction period should be about one and a half years. We use the subjective initiative of the project to complete the construction of the entire project in the three months of the contract period, which reflects the 'two -voyage speed'. After completion of production, ensure that Xiaopeng Automobile and AVIC Lithium Electricity projects are put into operation as scheduled. "

(Hubei Taiwan reporter Li Hui, correspondent Zhang Xiaolin and Liu Xiyan)

The copyright belongs to the original author and pays tribute to the original

- END -

Wuhan fully deal with the strongest rainfall into Meimei: more than 1600 people carry 500 sets of vehicles and equipment on the streets of San Town, as of 22 o'clock

Jimu Journalist Pan XizhengCorrespondent Li Peng Zhang KeOn the evening of the 27t...

The third -level government service in Hanyang District ushered in the "experiential consultation" members of the CPPCC

The Yangtze River Daily Da Wuhan Client September 23 (Reporter Wang Su Corresponde...