How to apply for the construction of electric vehicle charging facilities in the residential community?What should I do if the property obstructs?Authoritative answers are here!

Author:Published by Sichuan Time:2022.09.27

With the popularization rate of electric vehicles in citizens group, a few days ago, the Chengdu Housing and Construction Bureau and Chengdu Economic and Information Bureau jointly issued the "Further clarifying the responsibilities of property service enterprises to accelerate the construction announcement of" . How to apply for the construction of electric vehicle charging facilities in the residential community? What should the property be obstructed for no reason? Chengdu Housing and Construction Bureau gives an authoritative reply

1. Q: How can residents apply for self -use piles for residents who have been transferred to the residential area of ​​power supply companies?

Answer: The power supply and distribution facilities have been transferred to the residential community of power supply companies. The residents directly submit an application for the installation of charging facilities to the power supply enterprise. Because the power capacity cannot meet the installation requirements, the power supply enterprise provides solutions.

2. Question: In the case of insufficient power capacity of power supply and distribution facilities, in the case of insufficient power capacity, is there any other solutions in addition to implementing the solution of the "unified construction of the integrity" model?

Answer: The residential community that has not been transferred to the power supply enterprise for power distribution facilities can not meet the installation requirements in insufficient power capacity. It can also solve the way of conducting the volume of residential transformers in accordance with the law and the relevant funding of all owners in accordance with the law. , Support priority to adopt the "unified building management" model, and apply intelligent and orderly charging.

Question: After the evaluation, there are surplus available power capacity in the community. How do residents apply for their own pile construction? What are the application conditions and construction processes?

Answer: According to the results of the evaluation, the property service enterprise cooperates with the individual of the residents to carry out its own installation and construction in accordance with the order of the application, and establish a ledger to register.

(1) The "unified construction of unified management" model self -use pile construction

Application conditions: 1. Parking conditions. The leased parking spaces agreed by the owner's parking space or property owner (for more than one year);

2. Fire facilities. Underground, semi -underground and high -rise garage have the automatic fire alarm system, smoke exhaust facilities, automatic water spray fire extinguishing system, fire emergency lighting and evacuation indicator;

3. Introduction of third -party professional institutions with power deployment capabilities. Property service companies have signed a construction and operation agreement with third -party professional institutions.

Construction process: Signed a installation and use agreement with a third -party professional organization with power deployment capabilities, and third -party professional institutions are responsible for construction and later maintenance management and fulfill the responsibility of safety management.

(2) Self -use pile construction of the "self -construction and self -management" model

Application conditions: 1. Parking conditions. The leased parking spaces agreed by the owner's parking space or property owner (for more than one year);

2. Power capacity. The remaining power capacity of the community meets the installation requirements;

3. Fire protection facilities. Underground, semi -underground, and high -rise garage have the automatic fire alarm system, smoke discharge facilities, automatic water spray fire extinguishing system, fire emergency lighting and evacuation indicators.

Construction process: Application. The applicant holds an identity card, parking space certificate, car purchase contract, and "Application Form for Charging Facilities" to the property service enterprise; after checking and receiving a copy of the property service enterprise, the "application application form of the charging facility reported in the charging facility reported in 3 working days (Personal News) issued on the opinion and stamped.

Application. The applicant applied to the power grid company. Application materials: (1) ID card; (2) parking space certificate; (3) "Application Form for Charging Facilities" (property seal).

On -site survey. Within 1 working day after the application for the reporting of the power supply company, the applicant went to the site to conduct electricity consumption and construction feasibility survey to determine the electricity connection and safe location. The property service enterprise should actively cooperate.

Construction. The applicant organizes a qualified construction unit to organize construction and construction in accordance with the corresponding specifications; the applicant and the construction unit signed the "Self -use Pile Installation of Electric Vehicles (Applicants)", "Electric Vehicle Self -use Pile Installation and Installing Notes (Self -use Pile Installation Letter ( Construction can be carried out after "construction unit);

During the construction, the applicant shall select the construction of a qualified professional construction unit in accordance with the relevant requirements of the "Chengdu Electric Vehicle Charging Facilities Construction Technical Specification (2022 Edition)".

Install the watch. After the construction is completed, the applicant shall submit an application for completion inspection to the power grid company; the power grid company organizes the acceptance within 1 working day, issues acceptance opinions, and installs the electricity. The charging facilities (use) agreement (use) agreement ", which agreed to such as safety and responsibilities and responsibilities.

Maintenance management. The applicant shall fulfill the responsibility of the safety management subject. If the applicant maintains its own maintenance and management, it shall be maintained in accordance with relevant regulations; if a professional organization is commissioned to maintain management, the entrusted management contract shall be signed and the maintenance management shall be urged.

4. Q: What should I do if the property service company obstructs the installation of charging piles for no reason?

Answer: Property service enterprises are actively cooperating with residents' individuals and power supply enterprises in accordance with laws and regulations to conduct charging facilities in accordance with laws and regulations. Set up "thresholds" and not charge the cost of non -substantial service content. The city's negative behavior of the property service enterprise "zero tolerance" was found together, handled together, and notified together. If there is a situation involved in the negative behavior list, please reflect the residential construction department and the market supervision department.

Fifth, ask: Can property service companies charging a capacity increase?

Answer: If the owner of the community jointly decides to solve the problem of the installation requirements of charging pile by carrying out the transformer increase, and under the premise of authorizing the entrusted property service enterprise to implement the capacity, the property service enterprise can collect it in accordance with the charging standards decided by the owner's decision on behalf of the collection. Increased fees, the amount of increase fees charged requires separate accounts, and special funds are dedicated. Otherwise, property service companies shall not charge an increase in capacity. 6. Q: What fees can property service companies charge in the management activities of charging facilities?

Answer: In the management activities of charging facilities, property service companies can accept commission to provide services and charge the corresponding fees. For example: Our city encourages property service companies to accept charging facilities owners to entrust the operation and maintenance services of charging facilities. If the property service enterprise entrusts the operation and maintenance services of charging facilities, it shall sign the charging facility with the client in the principle of voluntary, fair and reasonable principles. Victorious service contracts, clarify service matters, content, quality requirements, charging standards and rights and obligations of both parties.

7. Q: Why should you buy the liability insurance for the additional self -use charging pile? How to buy?

Answer: In order to improve the ability of the owner of the pile owner to resist risks and the ability to pay afterwards, the city encourages the owner of the community to use the owner of the pile owner to purchase additional self -use charging pile liability insurance.

According to the "Exclusive Terms of New Energy Vehicle Commercial Insurance (Trial)" according to the China Insurance Industry Association on December 4, 2021, car owners can purchase additional self -use charging pile liability insurance on the basis of buying auto insurance additional liability insurance.

- END -

[Learn and implement the spirit of the 14th Provincial Party Congress] Join group chat!After listeni

(China Gansu.com)Editor in charge: Li Yuefan

After donating 8208 million, Henan Old Professor donated another 3 million!admire!

Henan Agricultural UniversityThe 120th anniversary celebration is about to usher i...