Fushan speed, complete this road in 14 hours!

Author:Yantai Daily Time:2022.09.28

At 9 am on September 28, the reporter came to the Chongwen Bridge on the East East Road in Hebin, Fushan District. The newly repaired black asphalt pavement on the new Riverside East Road was renewed, and a road surface extended straight. After 14 hours of continuous tension construction, the road constructed by the Fushan District Transportation Bureau has completed a gorgeous "transformation", and the travel of local residents will be more convenient.

Riverside East Road, which is 2.2 kilometers long and 17 meters wide, was founded in the late 1990s and disrupted for a long time. Because of its place on the east bank of the hipping river, the three villages must be relocated. The traffic flow is large. Large, causing serious damage. In order to alleviate the pressure of citizens' traffic and provide a convenient travel environment, the road was closed from 12 noon on September 27, and the upgrade and transformation project officially started.

The Fushan District Transportation Bureau dispatched more than 30 engineering teams, dispatched 3 pavement machines, 4 roadside machines, 6 transport vehicles, and other construction machinery. Finally, the construction task was completed at 2:00 in the morning. It took only 14 hours to complete the upgrade and reconstruction of Riverside East Road with a total length of 2.2 kilometers, and once again ran out of the "Fushan Traffic Speed", creating a "Fushan Traffic Miracle".

In the video, the reporter saw that at 2 am, the lights were bright, the machine was rumbling, and the 17 -meter -wide road arranged for three paving machines to work at the same time. The employees and construction personnel of the Fushan District Transportation Bureau are stepping up construction and construction. Everyone is busy and tired. For 14 hours, a 2.2 km long and 17 -meter asphalt road was paved.

"It is the first time since I have been working in my career overnight! Workers have been doing it from 12 o'clock to the end. Originally, I planned to use two nights to finish it, but considering the convenience of citizens' travel and avoiding the peak period, we we were at the peak period. We Fighting overnight. "Li Ming, deputy director of the Fushan District Transportation Service Center, said with a smile.

In 14 hours, the leaders of the Fushan District Transportation Bureau attached great importance to the project, and the "nail" was on the front line of the construction site to coordinate and solve the problems in the construction of the project in a timely manner. "We spread out various construction equipment and vehicles, cross -construction, and multi -point peak construction to ensure the progress of the project. While arranging special supervision units for supervision, organize technical personnel to guide the operation on the spot to ensure high standards and high -quality construction construction "Li Ming said.

The avenue is new and the world is new. In the future work, the Fushan District Transportation Bureau will use the sense of mission and responsibility of "rejuvenating and rejuvenating the Ru, responsible for me", forge ahead, pragmatic for progress, and promote the construction of Fushan's transportation at a high quality. Beautiful Xinfu Mountain contributes. (YMG All -Media Reporter Zou Chunxia Correspondent Zhang Haitao Photography Report)

- END -

Lanzhou City eliminates unreasonable traffic bayonet settings to ensure smooth road transportation channels

How to ensure the smooth transportation of transportation in the prevention and co...

[New Era of Entrusted New Journal] Gao Tai: "Science and Technology Courtyard" to serve the overall situation of rural revitalization

Rural revitalization relies on science and technology, and science and technology ...