Xiaoshan Xiaoshui answered netizens (9) | Setting the sewage port not only requires the approval of the ecological environment department, but also the water administrative department for approval?

Author:Ecological environment Time:2022.09.03

"Xiaoshan Xiaoshui Answer Netizen asked" to meet you again! What are the contents of this issue? Let's take a look together ~

barley

Setting the sewage port not only requires the approval of the ecological environment department, but also the water administrative department for approval?

Xiaoshan Xiaoshui Answer:

In 2018, institutional reforms, the management responsibilities of the sewage outlet settings of the river are transferred from the Ministry of Water Resources to the Ministry of Ecology and Environment. In accordance with the relevant provisions of the "Decision of Adjustment of Administrative Organs' Responsibilities" of the State Council's State Council's Institutions Reform involved in the reform of the State Council's institutions ", before the current laws and regulations have been revised, the relevant laws and regulations have been adjusted, The Ministry of Ecology and Environment aftermed. According to the "Notice of the General Office of the State Council on the Management of the Management of Comprehensive Implementation of Administrative License" (National Office [2022] No. 2), the implementation agencies of newly built, rebuilt or expand the approval of the sewage outlets are: Supervision and management agencies, provincial and district -level municipal and county -level ecological environment departments.

Cao Xiaofan

Article 67 of the Water Law and Article 84 of the Water Pollution Prevention Law, who applied first?

Xiaoshan Xiaoshui Answer:

According to Article 29 of the Administrative Penalty Law, if the same illegal acts that violate the "Water Law" and the "Water Pollution Prevention Law" shall be imposed and punished shall be imposed in accordance with the high amount of fine.

Attachment: Article 67 of the "Water Law" to set up sewage ports in the drinking water source protection area, the local people's governments at or above the county level are ordered to demolish and restore the original state of time; Original, and fined a fine of more than 100,000 yuan.

- END -

49.74 kWh!Hengyang City's industrial power in the first half of the year is third in the province

Hengyang News Network News Correspondent Zhang Yan reporter Zhu Min reported on July 9, the reporter learned from the Hengyang Development and Reform Commission that since this year, Hengyang City has

Battle "epidemic" big test!Resolve strict control and humanization appeal contradictory

China Well -off Network Exclusive SpecialtyText | Well -off · China Well -off repo...