Grasping the construction period, grabbing the construction of the high -speed Changning section of the Ivide high -speed Changning section, press the "fast -forward key" 丨 go all out to fight for the economy to build

Author:Cover news Time:2022.09.27

Zhang Baolin Cover Journalist Wu Xuemei

In the past few days, the construction of the 2nd standard section of the IVEM highway -the leading hub to Shuanghe Town, Changning County, Yibin, Sichuan, the construction of the Camellia Camellia Tunnel section has been accelerated. Target task.

"The design of the Camellia Tunnel is 6.3 kilometers in length, and it has been dug 5.2 kilometers smoothly, and the remaining 1.1 kilometers." On September 26, the construction site of the left hole of the IKEA Camellia Tunnel was brightly lit, and the workers were pouring concrete in the flat layer of the tunnel.

The camellia tunnel located in Shuanghe Town is a key control project of the 2nd bid section of the IVE highway, and it is also one of the special tunnels across the line. At present, the tunnels have more than 5.2 kilometers on the left and right double caves, and 82%of the total excavation input is completed.

"We put more than 300 people on site construction staff, and took 24 -hour shift operations to go all out to promote construction construction to ensure smoothly in April next year." Wang Xilin, chairman of the union chairman of the 2nd bidding section of the Yiwei Highway, told reporters.

It is understood that the 2nd bid between the IVEM highway starts from the leading hub in Shuanghe Town, Changning County, and ends at the exit of the Camellia Tunnel in the Shanhahua Tunnel in Dianxian Town, Shexian County, with a total length of 13.991 kilometers. There are 18 bridges across the line, 2 tunnels, and 1 hub interoperability, of which the main line bridge is 3.703 kilometers. As of now, the bid section has completed 1.446 million square meters and 551,000 cubic meters of filling, and 75%of the total project has been completed.

"At this stage, the key project of our IKEA Highway 2 is the prefabricated and erection of the bridge." Liu Dong, Minister of the Engineering Department of the 2nd Bid Project Department of the IKE highway, said that 1206 tablets, as of now, the main line beam has been set up 440 pieces, and 19 tablets are set up. The construction unit has invested more than 600 labor personnel to grab the work period to ensure that all the main line beams are erected before the Spring Festival, and 90%of the leading beams of the leading beams are completed.

- END -

More than 20 signal transmitters of the mall and banks overnight were stolen by the police to hear the police and quickly solved the case

After obtaining unjust money through illegal means, it is difficult to escape the ...

Yiyuan two roads should be repaired

Public sueYiyuan County Zizhong Road Road Daping Project (Zichuan Berma to Sancha)...